OpenNAOE homeHydrostatics & StabilityChapter 6Version 1.0 Send feedback

Figures and tables have more room in landscape.

Chapter 6: Trim and longitudinal stability

Version 1.0 · last revised 6 November 2026 · corrections

Prologue: the Steel Flower in the Welland Canal

On 28 April 1996 the bulk carrier Steel Flower, 222.48 m long, arrived at Port Colborne to go down the Welland Canal with a cargo of corn loaded at Toledo, Ohio. It was drawing 8.11 m forward and 7.95 m aft. The St. Lawrence Seaway Authority then allowed no ship a draught of more than 8.00 m, so at the bow the ship was 11 cm too deep1. Attempts to correct its draught in Lock 8 failed, and the Authority ordered the ship to a wharf. There the crew reduced the trim by the head, and when the ship left the wharf that evening it was drawing 8.03 m forward and 8.02 m aft. It was now almost level but still deeper than the limit, and the Authority gave it special permission to continue1.

About two hours later, near Mile 11 of the canal, the Steel Flower stopped answering its helm. The pilot put the helm hard over and used the bow thruster and then the engine astern, but the ship kept heading for the west bank at a shallow angle and touched the bottom at the side of the channel. Divers later found an indentation 8 m long, with four fractures, at the turn of the bilge on the port side forward. The investigators concluded that the ship had been drawing more than the Seaway draught, and that it had most likely touched the bottom because of suction towards the bank and the bottom1.

Levelling the ship had lifted its bow by 8 cm and sunk its stern by 7 cm (Fig. 6.1). A ship in which a weight is moved turns, to first order in a small change of trim, about the centroid of its waterplane. The draught there is approximately unchanged. How far each end rises or sinks depends on where that centre lies. In Sec. 6.4.3 we will return to the Steel Flower and see why, for any likely position of that centre, no movement of weight on board could have brought both of its ends to 8.00 m.

A graph of draught against position along the ship, from the after perpendicular at the left to the forward perpendicular at the right, with the draught axis running from 7.90 m to 8.15 m. A solid sloping line rises from 7.95 m at the after perpendicular to 8.11 m at the forward perpendicular, labelled on arrival at Port Colborne. A dashed, nearly horizontal line runs from 8.02 m aft to 8.03 m forward, labelled on leaving the wharf. A dotted horizontal line at 8.00 m is labelled Seaway maximum draught, 8.00 m. Both lines lie above the dotted line at the bow, and the dashed line lies above it along the whole length.

Figure 6.1 Draughts of the Steel Flower on arrival at Port Colborne and on leaving the wharf, against the Seaway maximum of 8.00 m, from the report of the Transportation Safety Board of Canada1. The draught axis is enlarged.

Chapter 5 dealt mostly with heel. A mass moved along the ship, or loaded or discharged away from the centre of flotation, changes the trim, and the draughts at the two ends then determine whether the ship can enter a lock and whether its propeller stays immersed. In this chapter we will calculate these draughts after a change of loading and for a complete loading condition, starting from the marks on the hull and using the equivalent even-keel draught of Chapter 3 and the moment to change trim one centimetre of Chapter 4. At the end we will look at the longitudinal stability of an intact ship, which is very large, and at the few cases in which it can still matter.

In this chapter

By the end of this chapter you will be able to:

What it assumes. You need the axes and trim of Sec. 1.3 and the TPC of Sec. 3.4.2. From Sec. 4.10 you need MCT 1 cm and the turning of a slightly trimmed ship about F.

A first reading. Sections 6.1 to 6.4, 6.5.1 to 6.5.3 and 6.5.6 carry the main thread. Sections 6.5.4, 6.5.5 and 6.6, on the second trim correction, the change of trim with the density of the water and longitudinal stability, can wait for a second reading. Table 6.3, which closes the technical sections, collects the signs and conditions of the main thread and belongs to the first.

6.1 Trim and the draughts

6.1.1 Draught at any point of a trimmed ship

With the conventions of Sec. 1.3, the draughts TAT_A and TFT_F are measured at the after and forward perpendiculars, and the trim is t=TA−TFt = T_A - T_F, positive when the ship is down by the stern. The trim angle θ\theta is given by tanθ=t/L\tan\theta = t/L, where LL is the length between perpendiculars, and lengths along the ship are measured forward from the AP. The three reference hulls of Chapter 1 have a straight keel with no designed drag, so at even keel the draughts at the two ends are equal.

Trim is stated as the length tt rather than as the angle. The draughts are what the marks show and what a lock or a berth limits, and an angle of trim means different draughts in ships of different lengths: an angle of 0.47° is a trim of 1 m in the Series 60 ship, 121.92 m long, and of 2.46 m in a ship 300 m long. For this reason the moment that changes the trim is tabulated per centimetre of trim, not per degree2.

A ship that is not bent has a straight keel, and the draught at any point between the perpendiculars lies on the straight line joining TAT_A and TFT_F. At a distance xx forward of the AP,

T(x)=TA−txL.(6.1)T(x) = T_A - t\,\frac{x}{L} . \qquad (6.1)

The deepest point of a straight keel is therefore at one of its ends, at the stern when the ship trims by the stern and at the bow when it trims by the head. A ship that is hogged or sagged has a curved keel and a midship draught that differs from the line through the end draughts, and Sec. 3.6.1 showed how the midship marks are used to allow for it. In this chapter the hull is taken as straight.

6.1.2 Reading the draught marks

As we saw in Sec. 1.2.6, the draughts of a ship in service are read from draught marks painted near the ends of the hull. The marks usually show keel draughts, measured from the underside of the keel, and they stand a short distance from the perpendiculars. The draughts of hydrostatic data may be measured from the moulded baseline or from the bottom of the keel, and the marks themselves may refer to another baseline, so the user has to know which2. Design data use moulded draughts at the perpendiculars, and two corrections are then needed before the readings can be used with them2,3.

The first correction is for the position of the marks. Let the aft marks stand at xax_a and the forward marks at xfx_f, and let their readings, each the mean of the port and starboard marks, be Ta′T_a' and Tf′T_f'. The two readings lie on the straight waterline of Eq. (6.1), so the trim between the perpendiculars is the trim between the marks scaled up to the length LL,

t=(Ta′−Tf′)Lxf−xa,(6.2)t = \left(T_a' - T_f'\right)\frac{L}{x_f - x_a} , \qquad (6.2)

and the draughts at the perpendiculars follow by moving along that line from each set of marks to its perpendicular,

TA=Ta′+txaL,TF=Tf′−tL−xfL.(6.3)T_A = T_a' + t\,\frac{x_a}{L} , \qquad T_F = T_f' - t\,\frac{L - x_f}{L} . \qquad (6.3)

The corrections are small, but they grow with the trim and with the distance of the marks from the perpendiculars4. The second correction is for the keel, and it is needed when the hydrostatic data are moulded. A keel draught exceeds the moulded draught by the thickness of the keel plate, or by the depth of a bar keel, and this thickness is subtracted from both draughts2.

6.1.3 Draught at the centre of flotation

Section 1.6 defined the centre of flotation F, the centroid of the waterplane, and Sec. 4.10.1 showed that a ship trimming slightly at constant displacement turns about F, which for this reason is known as the tipping centre4,5. The draught at F is then the equivalent even-keel draught, the draught at which the ship would float level with its displacement unchanged, also called the true mean draught4,5. By Eq. (6.1), the draught at F is

T(xF)=TA−txFL=TA+TF2+tL/2−xFL.(6.4)T(x_F) = T_A - t\,\frac{x_F}{L} = \frac{T_A + T_F}{2} + t\,\frac{L/2 - x_F}{L} . \qquad (6.4)

The second form shows that the mean of the two end draughts is the draught at F only when F lies amidships. In most ships F lies a little aft of amidships6. It lies up to about 3 % of the length forward of amidships in very full forms and up to about 3 % aft in fine forms5. On the Series 60 hull, a fine form, F lies 4 to 5 m aft of amidships at its loaded draughts, 3 to 4 % of the length. When such a ship trims by the stern, the mean of the end draughts is less than the draught at F, and when it trims by the head the mean is greater (Fig. 6.2). Entering the hydrostatic table with the mean of the end draughts would then give the wrong displacement. The difference is the mass of a thin layer between the two parallel waterplanes through F and through amidships. The correction to be added to the displacement read at the mean of the end draughts is 100TPC⋅t(L/2−xF)/L100\,\mathrm{TPC}\cdot t\,(L/2 - x_F)/L tonnes, with tt in metres, by the stern positive: it is negative when the ship trims by the head with F aft of amidships. In draught surveys it is called the first trim correction or the layer correction5,6. Equation (6.4) is exact for a straight waterline. While the trim is small, the draught at F is the equivalent even-keel draught, and the hydrostatic table entered there gives the displacement; at larger trims a second correction is needed.

Table 6.1 gives the hydrostatic values of the Series 60 ship from 5.2 m to 7.2 m, with the moment to change trim one centimetre. That moment is calculated from the second moment of the waterplane by Eq. (4.23), MCT1cm≈ρIL/(100L)\mathrm{MCT\,1\,cm} \approx \rho\,I_L/(100\,L), as in most hydrostatic tables, since that value does not depend on the position of G2. With BML\mathrm{BM}_\mathrm{L} in place of GML\mathrm{GM}_\mathrm{L}, the value is strictly an approximation to the MCT 1 cm of a loaded ship and could be labelled as such. For the Series 60 ship, with G about 2.5 to 3 m above B and BML\mathrm{BM}_\mathrm{L} about 140 m, the tabulated value is about 2 % too large. Tables also differ in the form of this column. Many give the moment to change trim one metre, a hundred times MCT 1 cm, and some give a volume moment3,6, ∇BML/L\nabla\,\mathrm{BM}_\mathrm{L}/L in m⁴/m. Others give a moment of force, computed from the weight instead of the mass6, so the title and unit of the column should be read before a value is used. In this hull and draught range, MCT 1 cm and TPC grow with the draught, and xFx_F moves aft as the waterplane becomes fuller aft. This is a common trend, described by Attwood, rather than a rule for every hull7.

Table 6.1 Hydrostatic values of the Series 60 hull, 121.92 m between perpendiculars, in sea water (ρ\rho = 1.025 t/m³), upright and at even keel. xBx_B and xFx_F are measured forward of the AP, and amidships is at 60.96 m; MCT 1 cm is ρIL/(100L)\rho\,I_L/(100\,L).

TT (m) Δm\Delta_m (t) TPC (t/cm) xBx_B (m) xFx_F (m) MCT 1 cm (t·m/cm)
5.2 6087.8 13.49 59.69 58.32 74.54
5.4 6358.8 13.61 59.63 58.04 76.26
5.6 6632.3 13.74 59.56 57.73 78.22
5.8 6908.5 13.88 59.48 57.39 80.39
6.0 7187.7 14.03 59.39 57.02 82.75
6.2 7469.9 14.18 59.29 56.68 85.07
6.4 7754.9 14.32 59.19 56.38 87.24
6.6 8042.5 14.45 59.09 56.13 89.26
6.8 8332.7 14.57 58.98 55.89 91.34
7.0 8625.5 14.71 58.87 55.65 93.54
7.2 8921.0 14.84 58.76 55.42 95.84

Two panels in rows. (a) The Series 60 hull in profile, with heights drawn three times as large as lengths, floating at a waterline that is deeper at the bow than at the stern. Vertical lines mark the after perpendicular at the left, the forward perpendicular at the right and amidships. The draughts T_A at the after perpendicular and T_F at the forward perpendicular are marked with arrows from the baseline to the waterline. Short vertical bars a little inside each perpendicular mark the positions of the aft and forward draught marks. A small circle on the waterline, a little aft of amidships, marks the centre of flotation F, with an arrow giving the draught at F. (b) The draughts of panel (a) as a straight line on a graph of draught against distance from the after perpendicular: two dots at the positions of the marks give the readings, and the line through them is extended to the two perpendiculars to give T_A = 5.674 m and T_F = 6.440 m. A horizontal dashed line at the draught at F, 6.032 m, crosses the sloping line above the position of F, and the mean of the two end draughts, 6.057 m, is marked amidships, a little above the dashed line.

Figure 6.2 Draughts of the Series 60 ship trimmed 0.766 m by the head: (a) the hull, with heights three times as large as lengths; (b) the waterline through the readings at the marks, extended to the perpendiculars.

Example 6.1. The draughts and displacement from the marks. The Series 60 ship, 121.92 m between perpendiculars, arrives at port in sea water. Its aft draught marks stand 2.80 m forward of the AP and the forward marks 1.72 m aft of the FP, and they read keel draughts; the keel plate is 20 mm thick. The mean readings of the port and starboard marks are 5.712 m aft and 6.450 m forward. Find the moulded draughts at the perpendiculars, the trim, the draught at the centre of flotation and the displacement mass, using Table 6.1, and compare it with the value given by the mean of the end draughts.

Show full solution

Solution.

The trim. The marks are 121.92−2.80−1.72=117.40121.92 - 2.80 - 1.72 = 117.40 m apart, and the trim between the perpendiculars is

t=(5.712−6.450)×121.92117.40=−0.738×1.0385=−0.766m,t = (5.712 - 6.450) \times \frac{121.92}{117.40} = -0.738 \times 1.0385 = -0.766\ \mathrm{m},

a trim of 0.766 m by the head.

The draughts at the perpendiculars. Moving along the waterline from each set of marks to its perpendicular, the keel draughts are

TA=5.712−0.766×2.80121.92=5.712−0.018=5.694m,TF=TA−t=5.694+0.766=6.460m,\begin{aligned}T_A &= 5.712 - 0.766 \times \frac{2.80}{121.92} = 5.712 - 0.018 = 5.694\ \mathrm{m}, \\ T_F &= T_A - t = 5.694 + 0.766 = 6.460\ \mathrm{m},\end{aligned}

and the moulded draughts, 0.020 m less, are TA=5.674T_A = 5.674 m and TF=6.440T_F = 6.440 m.

The draught at F. The mean of the end draughts is 6.057 m, where the table gives xF=57.02−0.285×0.34=56.92x_F = 57.02 - 0.285 \times 0.34 = 56.92 m, and

T(xF)=5.674+0.766×56.92121.92=5.674+0.358=6.032m.T(x_F) = 5.674 + 0.766 \times \frac{56.92}{121.92} = 5.674 + 0.358 = 6.032\ \mathrm{m}.

At 6.032 m, xFx_F is 56.97 m, which changes T(xF)T(x_F) by less than 1 mm.

The displacement. In the table, 6.032 m lies 0.16 of the way from 6.0 m to 6.2 m, so

Δm=7187.7+0.16×282.2=7232.9t.\Delta_m = 7187.7 + 0.16 \times 282.2 = 7232.9\ \mathrm{t}.

With the mean of the end draughts, 6.057 m, the table would give 7187.7+0.285×282.2=7268.17187.7 + 0.285 \times 282.2 = 7268.1 t, 35.2 t too much.

Comment. The weight table of this arrival condition gives 7236 t. Most of the remaining 3.1 t is a second-order effect of the trim.

6.2 Change of trim due to a shift of weight

6.2.1 Trimming moment and change of trim

We saw in Sec. 4.10.2 that when a mass mm already on board is moved a distance dd along the ship, G moves parallel to it through md/Δmm\,d/\Delta_m, and the ship trims until the centre of buoyancy lies under the new position of G. The moment mdm\,d, a moment of mass in t·m, is the trimming moment, and dividing it by the moment to change trim one centimetre, MCT 1 cm, gives the change of trim in centimetres. With the mass moved from x1x_1 to x2x_2, the change of trim is

δt=−m(x2−x1)MCT1cm(cm),(6.5)\delta t = -\frac{m\,(x_2 - x_1)}{\mathrm{MCT\,1\,cm}} \quad (\text{cm}) , \qquad (6.5)

with mm in tonnes and the lengths in metres. A mass moved forward, x2>x1x_2 > x_1, gives a negative change, that is, a change of trim by the head, and a mass moved aft gives a change by the stern4,6. MCT 1 cm is read at the draught at F, since the shift does not change it.

Historical note: the moment to change trim one inch

In his textbook of 1899, Attwood found the change of trim in inches, dividing the moment of the weight moved, in foot-tons, by the moment to change trim one inch, the displacement in tons times GML\mathrm{GM}_\mathrm{L} over twelve times the length in feet. In many ships, he noted, BML\mathrm{BM}_\mathrm{L} and with it GML\mathrm{GM}_\mathrm{L} are roughly equal to the length, and the moment is then about a twelfth of the displacement, more in ships that are long in proportion to their draught7. In tonnes and centimetres his rule makes MCT 1 cm about a hundredth of the displacement mass. For the Series 60 ship at 7707 t it gives 77 t·m/cm against 86.87 t·m/cm from Table 6.1, because the ship’s BML\mathrm{BM}_\mathrm{L} of about 137 m exceeds its length of 121.92 m.

6.2.2 Change of draught at each end

As the waterline turns about F, the draught at F does not change, and the two ends move in opposite directions by amounts in proportion to their distances from F (Fig. 6.3). The AP is xFx_F aft of F and the FP is L−xFL - x_F forward of it, so a change of trim δt\delta t changes the draughts by

δTA=δtxFL,δTF=−δtL−xFL,(6.6)\delta T_A = \delta t\,\frac{x_F}{L} , \qquad \delta T_F = -\,\delta t\,\frac{L - x_F}{L} , \qquad (6.6)

whose difference is the change of trim4, δTA−δTF=δt\delta T_A - \delta T_F = \delta t. A change of trim of one centimetre is thus shared between the two ends, and neither end moves by the whole centimetre. When F lies amidships, each end moves by half of it. When F lies aft of amidships, the forward draught changes more than the aft draught. In the Series 60 ship in its departure condition, with F at 56.43 m, each centimetre of trim moves the stern by 0.46 cm and the bow by 0.54 cm. The mean of the two end draughts then changes by δt(xF−L/2)/L\delta t\,(x_F - L/2)/L although the displacement has not changed. For this reason the change of trim should not be divided equally between the two ends7, even though the error of doing so is minor for a small change of trim.

A schematic profile of the Series 60 hull, heights drawn three times as large as lengths, with two waterlines that cross at the centre of flotation F a little aft of amidships. The dashed waterline is level; the solid waterline is lower at the bow and higher at the stern. A mass drawn dashed on the deck forward has been moved to a solid block on the deck aft, with an arrow pointing aft. At the after perpendicular an arrow marks the rise of the waterline, delta T_A, and at the forward perpendicular an arrow marks its fall, delta T_F. The distances from the AP to F, x_F, and from F to the FP, L minus x_F, are dimensioned below the hull.

Figure 6.3 A mass moved aft, with the waterline turning about F. Schematic, with the trim enlarged and heights three times as large as lengths.

Predict 6.1. The Series 60 ship displaces 7707 t and floats level, with F at 56.43 m forward of the AP. A 60 t item of deck cargo is moved aft, from 105.68 m to 20.90 m forward of the AP. Decide whether the mean of the two end draughts changes, and if so in which direction, before you work through Example 6.2.

Check your prediction

Answer. It falls. The ship turns about F, which lies 4.53 m aft of amidships, so the bow rises more than the stern sinks, and the mean of the end draughts falls by about 2.2 cm.

Example 6.2. Moving deck cargo aft. The Series 60 ship displaces 7707 t and floats level in sea water. A 60 t item of deck cargo is moved aft, from 105.68 m to 20.90 m forward of the AP. Find the change of trim and the new draughts at the perpendiculars, using Table 6.1.

Show full solution

Solution.

The hydrostatic values. In the table, 7707 t lies 237.1/285.0=0.83237.1/285.0 = 0.83 of the way from 6.2 m to 6.4 m, so the ship floats at 6.366 m, where the table gives

MCT1cm=85.07+0.83×2.17=86.87t⋅m/cm,xF=56.68−0.83×0.30=56.43m.\begin{aligned}\mathrm{MCT\,1\,cm} &= 85.07 + 0.83 \times 2.17 = 86.87\ \mathrm{t{\cdot}m/cm}, \\ x_F &= 56.68 - 0.83 \times 0.30 = 56.43\ \mathrm{m}.\end{aligned}

The change of trim. The mass moves 105.68−20.90=84.78105.68 - 20.90 = 84.78 m aft, so

δt=−60×(20.90−105.68)86.87=5086.886.87=58.6cm,\delta t = -\frac{60 \times (20.90 - 105.68)}{86.87} = \frac{5086.8}{86.87} = 58.6\ \mathrm{cm},

by the stern.

The draughts. The ends move in proportion to their distances from F,

δTA=58.6×56.43121.92=27.1cm,δTF=−58.6×65.49121.92=−31.5cm,\begin{aligned}\delta T_A &= 58.6 \times \frac{56.43}{121.92} = 27.1\ \mathrm{cm}, \\ \delta T_F &= -58.6 \times \frac{65.49}{121.92} = -31.5\ \mathrm{cm},\end{aligned}

so that TA=6.366+0.271=6.637T_A = 6.366 + 0.271 = 6.637 m and TF=6.366−0.315=6.051T_F = 6.366 - 0.315 = 6.051 m.

Comment. The mean of the two end draughts has fallen by 58.6×4.53/121.92=2.258.6 \times 4.53/121.92 = 2.2 cm although the displacement has not changed, because F lies 4.53 m aft of amidships and the bow rises more than the stern sinks. Solved on the hull, the level draught is 6.367 m, and the new draughts are 6.639 m aft and 6.048 m forward, within 3 mm of these values.

Animation 6.1 shows the Series 60 ship as a mass travels slowly along its deck from forward to aft and back. The waterline turns about F, and the draught there changes by less than 1 cm while the two ends rise and fall by about a metre.

Animation 6.1 The Series 60 ship at its departure displacement while 200 t moves along the deck between 100 m and 20 m forward of the AP, each frame an equilibrium of the hull. Above, the hull, heights three times as large as lengths, with the waterline turning about F; below, the draughts at the perpendiculars and at F, solved on the hull (solid) and by Eqs. (6.5) and (6.6) (dashed). The ends rise and fall by about a metre while the draught at F changes by less than 1 cm.

6.3 Change of trim due to adding or removing weights

6.3.1 Sinkage and change of trim

When a mass is loaded, the ship sinks as well as trims. Section 3.4.4 showed how to separate the two effects. A mass mm placed on the vertical through F makes the ship sink bodily, without trim, by

δT=mTPC(cm).\delta T = \frac{m}{\mathrm{TPC}} \quad (\text{cm}) .

Moving the mass from F to its actual position at xx then trims the ship as in Sec. 6.2, by

δt=m(xF−x)MCT1cm(cm),(6.7)\delta t = \frac{m\,(x_F - x)}{\mathrm{MCT\,1\,cm}} \quad (\text{cm}) , \qquad (6.7)

by the stern when the mass lies aft of F4,6. With the two changes added (Fig. 6.4), the draughts at the ends change by

δTA=δT+δtxFL,δTF=δT−δtL−xFL.(6.8)\delta T_A = \delta T + \delta t\,\frac{x_F}{L} , \qquad \delta T_F = \delta T - \delta t\,\frac{L - x_F}{L} . \qquad (6.8)

A mass discharged is entered as negative. The ship then rises, and it trims by the stern if the mass was taken from forward of F and by the head if it was taken from aft of F. For several masses loaded and discharged together, their sum gives the sinkage and the sum of their moments about F gives the change of trim, usually set out in a table with a column of masses and a column of moments4,5. TPC, xFx_F and MCT 1 cm are taken at the initial draught when the total mass is small. When it is not, they are taken at the draught midway between the initial and final draughts at F4, or the whole condition is worked again from its weight table.

Two schematic panels in rows of the Series 60 hull in profile, heights drawn three times as large as lengths. (a) A mass m is placed on the vertical through the centre of flotation F; the ship sinks bodily from the dashed waterline to a parallel solid waterline, an arrow pointing up the hull marking the rise of the waterline, the sinkage m over TPC. (b) The mass m is moved forward from F to its position at x; the solid waterline of panel (a), now dashed, turns about F to a new solid waterline, deeper forward and shallower aft, and an arrow marks the moment m times (x minus x_F).

Figure 6.4 A mass loaded forward of F, in two steps: (a) placed over F, it sinks the ship bodily by m/TPC; (b) moved forward to x, it trims the ship about F. Schematic, with sinkage and trim enlarged and heights three times as large as lengths.

Example 6.3. Loading deck cargo forward. In its departure condition the Series 60 ship displaces 7707 t and floats level in sea water at 6.366 m, the draught that Table 6.1 gives for this displacement. The ship loads 150 t of deck cargo centred 95.00 m forward of the AP. Find the new draughts at the perpendiculars, using the table.

Show full solution

Solution.

The hydrostatic values. At 6.366 m, the table gives TPC = 14.18 + 0.83 × 0.14 = 14.30 t/cm, xFx_F = 56.43 m and MCT 1 cm = 86.87 t·m/cm.

The sinkage. δT=150/14.30=10.5\delta T = 150/14.30 = 10.5 cm.

The change of trim. The cargo lies 95.00−56.43=38.5795.00 - 56.43 = 38.57 m forward of F, so

δt=150×(56.43−95.00)86.87=−5785.586.87=−66.6cm,\delta t = \frac{150 \times (56.43 - 95.00)}{86.87} = -\frac{5785.5}{86.87} = -66.6\ \mathrm{cm},

by the head.

The draughts. Adding the sinkage and the shares of the change of trim,

δTA=10.5−66.6×56.43121.92=10.5−30.8=−20.3cm,δTF=10.5+66.6×65.49121.92=10.5+35.8=46.3cm,\begin{aligned}\delta T_A &= 10.5 - 66.6 \times \frac{56.43}{121.92} = 10.5 - 30.8 = -20.3\ \mathrm{cm}, \\ \delta T_F &= 10.5 + 66.6 \times \frac{65.49}{121.92} = 10.5 + 35.8 = 46.3\ \mathrm{cm},\end{aligned}

so that TA=6.163T_A = 6.163 m and TF=6.829T_F = 6.829 m.

Comment. The cargo, 2 % of the displacement, sinks the bow by 46 cm and lifts the stern by 20 cm. Solved on the hull, the draughts are 6.157 m aft and 6.834 m forward.

6.3.2 Loading without changing the draught at one end

A ship sometimes has to load while one of its draughts is held at a limit. A ship at a berth or in a channel whose depth limits the stern, for example, may load only where the extra mass leaves the aft draught unchanged4. The sinkage deepens both ends, and the change of trim then has to lift the stern as much as the sinkage lowers it. Extended to any point, Eq. (6.8) gives the change of the draught at a point x0x_0 caused by a mass loaded at xx as δT+δt(xF−x0)/L\delta T + \delta t\,(x_F - x_0)/L. Setting this change to zero gives the position at which the mass leaves the draught at x0x_0 unchanged2,

(x−xF)(xF−x0)=MCT1cm⋅LTPC.(6.9)(x - x_F)(x_F - x_0) = \frac{\mathrm{MCT\,1\,cm}\cdot L}{\mathrm{TPC}} . \qquad (6.9)

The mass and the point lie on opposite sides of F. For the aft draught, x0=0x_0 = 0, the mass goes MCT1cm⋅L/(TPC⋅xF)\mathrm{MCT\,1\,cm}\cdot L/(\mathrm{TPC}\cdot x_F) forward of F, and for the forward draught, x0=Lx_0 = L, it goes MCT1cm⋅L/[TPC(L−xF)]\mathrm{MCT\,1\,cm}\cdot L/[\mathrm{TPC}\,(L - x_F)] aft of F4,5. The position does not depend on the mass, as long as the mass is small enough for TPC and MCT 1 cm to stay constant. With MCT 1 cm from ρIL/(100L)\rho\,I_L/(100\,L) and TPC=ρAW/100\mathrm{TPC} = \rho\,A_W/100, the right-hand side of Eq. (6.9) is IL/AWI_L/A_W, the square of the radius of gyration of the waterplane about F. It is L2/12L^2/12 for a box, L2/20L^2/20 for the Wigley hull and about 741 m², or (27.2 m)², for the Series 60 ship in its departure condition. For this ship the changes of the two end draughts are straight lines in the position of the mass, and each crosses zero at one of the two positions (Fig. 6.5).

A graph of the change of draught, in centimetres, against the position along the ship at which 100 t is loaded, from the after perpendicular to the forward perpendicular, for the Series 60 ship in its departure condition. A rising straight line gives the change of the forward draught and a falling line the change of the aft draught; they cross at the centre of flotation, at 56.43 m, where both equal the bodily sinkage of 7.0 cm. The falling line crosses zero at 69.56 m, labelled aft draught unchanged, and the rising line crosses zero at 45.12 m, labelled forward draught unchanged.

Figure 6.5 Change of the draughts at the perpendiculars when 100 t is loaded at a position along the Series 60 ship in its departure condition, by Eq. (6.8).

Predict 6.2. The Series 60 ship in its departure condition is to load 100 t without changing the aft draught. Decide whether the mass should go forward or aft of F, and estimate how far from F, before you read Example 6.4.

Check your prediction

Answer. Forward of F. The sinkage deepens both ends, so the change of trim has to lift the stern, and only a mass forward of F trims the ship by the head. The distance is 13.13 m.

Example 6.4. Loading without sinking the stern. In its departure condition the Series 60 ship displaces 7707 t and floats level in sea water at 6.366 m, the draught that Table 6.1 gives for this displacement, with TPC = 14.30 t/cm, xFx_F = 56.43 m and MCT 1 cm = 86.87 t·m/cm. The ship is to load 100 t without changing its aft draught. Find where the mass must be placed and the new forward draught.

Show full solution

Solution.

The position. By Eq. (6.9) with x0=0x_0 = 0,

x−xF=86.87×121.9214.30×56.43=10,591.2806.9=13.13m,x - x_F = \frac{86.87 \times 121.92}{14.30 \times 56.43} = \frac{10{,}591.2}{806.9} = 13.13\ \mathrm{m},

so the mass goes 13.13 m forward of F, at x=56.43+13.13=69.56x = 56.43 + 13.13 = 69.56 m.

The forward draught. The sinkage is 100/14.30=6.99100/14.30 = 6.99 cm, and the change of trim is

δt=100×(−13.13)86.87=−15.11cm.\delta t = \frac{100 \times (-13.13)}{86.87} = -15.11\ \mathrm{cm}.

Then δTA=6.99−15.11×56.43/121.92=6.99−6.99=0\delta T_A = 6.99 - 15.11 \times 56.43/121.92 = 6.99 - 6.99 = 0, as required, and

δTF=6.99+15.11×65.49121.92=6.99+8.12=15.11cm,\delta T_F = 6.99 + 15.11 \times \frac{65.49}{121.92} = 6.99 + 8.12 = 15.11\ \mathrm{cm},

so that TF=6.366+0.151=6.517T_F = 6.366 + 0.151 = 6.517 m.

Comment. The forward draught increases by the whole change of trim, because the aft draught does not change. Solved on the hull, the draughts are 6.366 m aft and 6.518 m forward.

6.3.3 Loading or discharging to required draughts

A more general problem is to finish loading at given draughts, for example level at a given draught. Two quantities are then fixed, the change of the draught at F and the change of trim, and two masses can be found, or one mass and its position. With masses mPm_P and mQm_Q loaded at xPx_P and xQx_Q, the sinkage and the change of trim give two equations,

mP+mQ=TPC⋅δT,mP(xF−xP)+mQ(xF−xQ)=MCT1cm⋅δt,(6.10)m_P + m_Q = \mathrm{TPC}\cdot\delta T , \qquad m_P\,(x_F - x_P) + m_Q\,(x_F - x_Q) = \mathrm{MCT\,1\,cm}\cdot\delta t , \qquad (6.10)

with δT\delta T and δt\delta t in centimetres4,5.

Example 6.5. Finishing level. During loading in sea water, the Series 60 ship floats at 6.20 m aft and 5.95 m forward. 300 t of cargo remains to be loaded, in hold 2, centred 91.28 m forward of the AP, and in hold 4, centred 56.03 m forward of the AP. Find how much should go into each hold for the ship to finish level, and its final draught, using Table 6.1.

Show full solution

Solution.

The initial draught at F. The mean of the end draughts is 6.075 m, where the table gives xF=57.02−0.375×0.34=56.89x_F = 57.02 - 0.375 \times 0.34 = 56.89 m. The trim is 0.25 m by the stern, so

T(xF)=6.20−0.25×56.89121.92=6.20−0.117=6.083m.T(x_F) = 6.20 - 0.25 \times \frac{56.89}{121.92} = 6.20 - 0.117 = 6.083\ \mathrm{m}.

The hydrostatic values. At 6.083 m the TPC is 14.09 t/cm, so 300 t sinks the ship about 21 cm. Because this is not small, TPC, xFx_F and MCT 1 cm are read midway through the loading, at about 6.19 m:

TPC=14.17t/cm,xF=56.70m,MCT1cm=84.95t⋅m/cm.\mathrm{TPC} = 14.17\ \mathrm{t/cm}, \qquad x_F = 56.70\ \mathrm{m}, \qquad \mathrm{MCT\,1\,cm} = 84.95\ \mathrm{t{\cdot}m/cm}.

The two masses. The trim must change by 25 cm by the head, δt=−25\delta t = -25 cm. With m2m_2 in hold 2 and m4m_4 in hold 4, Eq. (6.10) gives

m2+m4=300,m2(56.70−91.28)+m4(56.70−56.03)=84.95×(−25)=−2123.8.\begin{aligned}m_2 + m_4 &= 300 , \\ m_2\,(56.70 - 91.28) + m_4\,(56.70 - 56.03) &= 84.95 \times (-25) = -2123.8 .\end{aligned}

Substituting m4=300−m2m_4 = 300 - m_2 in the second equation, −34.58m2+0.67(300−m2)=−2123.8-34.58\,m_2 + 0.67\,(300 - m_2) = -2123.8, so that

m2=2123.8+201.035.25=66.0t,m4=234.0t.m_2 = \frac{2123.8 + 201.0}{35.25} = 66.0\ \mathrm{t}, \qquad m_4 = 234.0\ \mathrm{t}.

The final draught. The ship sinks by 300/14.17=21.2300/14.17 = 21.2 cm and finishes level at 6.083+0.212=6.2956.083 + 0.212 = 6.295 m.

Comment. Solved on the hull, the ship finishes at 6.292 m aft and 6.299 m forward, level to within 7 mm.

6.4 Draught limits

The draughts of a ship have limits in both directions. The forward draught has to be enough to keep the bow from pounding in a seaway, and the aft draught enough to keep the propeller immersed, allowing for the fuel and stores used on the voyage2. Loading is usually planned to finish with the ship trimmed by the stern4. The International Convention for the Safety of Life at Sea, 1974 (SOLAS), asks that the stability information supplied to the master give the maximum permissible trim against draught, within which the ship meets its stability requirements8.

6.4.1 The deepest draught and the draught at F

Locks, canals, channels and berths set an upper limit on the draught of the ships that use them, and the limit applies to the deepest point of the ship. For a straight keel with nothing projecting below it, that point is the deeper of the two ends. A ship that is down by the head can bring its bow up by moving weight aft, and the stern then goes down. The draught at F does not change meanwhile, and one end of the ship is always at least as deep as the draught at F. Moving weight on board can therefore bring both ends within a limit only if the draught at F is already within it, and at best it leaves the ship level at that draught.

Within this small-trim model, when the draught at F exceeds the limiting draught TlimT_{\mathrm{lim}}, mass has to come off. The least mass that will do is 100TPC[T(xF)−Tlim]100\,\mathrm{TPC}\,[T(x_F) - T_{\mathrm{lim}}] tonnes, with the draughts in metres, taken off over F and with the remaining weight moved to bring the ship level. Discharging from one end only, with nothing moved on board, usually needs more, because the discharge must then also supply the trimming moment. The ship is not left level, and with the deeper end at the limit, the draught at F ends below it.

Example 6.6. A draught limit at a lock. The Series 60 ship arrives at a lock in sea water drawing 6.10 m aft and 6.62 m forward. The lock admits no ship drawing more than 6.30 m at any point. (a) Decide whether the ship can pass by moving cargo on board. (b) Find the least mass that must be discharged. (c) Find the mass that must be discharged from hold 1, centred 105.68 m forward of the AP, if no other cargo is moved, and the draughts after it. Use Table 6.1.

Show full solution

Solution.

(a) The draught at F. The mean of the end draughts is 6.36 m, where the table gives xF=56.68−0.80×0.30=56.44x_F = 56.68 - 0.80 \times 0.30 = 56.44 m. The trim is 0.52 m by the head, t=−0.52t = -0.52 m, so

T(xF)=6.10+0.52×56.44121.92=6.10+0.241=6.341m.T(x_F) = 6.10 + 0.52 \times \frac{56.44}{121.92} = 6.10 + 0.241 = 6.341\ \mathrm{m}.

This is more than 6.30 m, so no movement of cargo on board can bring both ends within the limit.

(b) The least discharge. The draught at F has to fall by 0.041 m. Midway between the two draughts, at about 6.32 m, the TPC is 14.26 t/cm, so at least 100×14.26×0.041=58.5100 \times 14.26 \times 0.041 = 58.5 t must come off, taken from over F, with other cargo moved to bring the ship level.

(c) Discharging from hold 1. At 6.32 m, the table gives xFx_F = 56.50 m and MCT 1 cm = 86.37 t·m/cm. Discharging mm tonnes from hold 1 lifts the ship bodily by m/14.26m/14.26 cm and trims it by the stern by m(105.68−56.50)/86.37=0.5694mm\,(105.68 - 56.50)/86.37 = 0.5694\,m cm. The forward draught must fall by 32 cm, so

m(114.26+0.5694×65.42121.92)=m(0.07013+0.30553)=32,m\left(\frac{1}{14.26} + 0.5694 \times \frac{65.42}{121.92}\right) = m\,(0.07013 + 0.30553) = 32 ,

which gives mm = 85.2 t. The aft draught then changes by

δTA=−85.214.26+85.2×0.5694×56.50121.92=−5.97+22.48=16.5cm,\delta T_A = -\frac{85.2}{14.26} + 85.2 \times 0.5694 \times \frac{56.50}{121.92} = -5.97 + 22.48 = 16.5\ \mathrm{cm},

so the ship passes at 6.265 m aft and 6.30 m forward.

Comment. Discharging from hold 1 without moving other cargo takes 26.7 t more than the least, and the ship rises more than the limit requires. The ship is left 3.5 cm by the head, with the draught at F at 6.341−0.060=6.2816.341 - 0.060 = 6.281 m, 1.9 cm below the limit. By Eq. (6.9) with the values at 6.32 m, a discharge at 69.57 m would leave the aft draught unchanged, and the stern sinks because hold 1 lies forward of that point. Cargo taken from between 45.21 m and 69.57 m would have lifted both ends. Solved on the hull, the ship floats at 6.272 m aft and 6.294 m forward after discharging 85.2 t from hold 1.

6.4.2 Projections below the keel, list and squat

The navigational draught (Sec. 1.2.3) fixes the depth of water that a ship needs2. With projections below the keel, the attitude that gives the least navigational draught is in general not level. Let projections reach p1p_1 below the keel at xp1x_{p1}, aft of F, and p2p_2 at xp2x_{p2}, forward of F. When weight is moved on board, the draught at F stays fixed, and the navigational draught is least when the ship draws equally at the two, T(xp1)+p1=T(xp2)+p2T(x_{p1}) + p_1 = T(x_{p2}) + p_2. By Eq. (6.1) this needs a trim

t=(p2−p1)Lxp2−xp1,t = \frac{(p_2 - p_1)\,L}{x_{p2} - x_{p1}} ,

by the stern when the forward projection is the deeper2. The waterline then runs parallel to the line joining the lowest points of the two projections, and the least navigational draught is the draught at F plus the depth of that line below the keel at F. This holds provided neither end of the keel is then deeper than the projections. The trim lowers one end of the keel, and when the projection on that side lies well inside the perpendicular, that end can become the deepest point, so the keel at that end is checked as well.

Suppose, for example, that the Series 60 ship in its departure condition, level at 6.367 m as solved on the hull, with F at 56.43 m and MCT 1 cm = 86.88 t·m/cm read from Table 6.1 at that draught, had propeller tips 0.30 m below the keel at 4.0 m forward of the AP and a sonar dome reaching 0.60 m below it at 112.0 m. Level, the ship would draw 6.967 m at the dome. Trimmed 0.339 m by the stern, which needs a trimming moment of 2942 t·m, it would draw 6.813 m at both, 15.4 cm less, while the keel at the AP would be at 6.524 m.

A list also deepens a ship. When the ship lists through a small angle φ\varphi about the centreline at the waterline, a point of its low side at a half-breadth yy and a height zz above the keel goes to a depth (T−z)cosφ+ysinφ(T - z)\cos\varphi + y\sin\varphi. In a box the deepest point is the bilge corner4,5, at 12Bsinφ+Tcosφ\tfrac12 B\sin\varphi + T\cos\varphi, so the draught grows by nearly 12Bsinφ\tfrac12 B\sin\varphi. In a ship with a rounded bilge the deepest point at a small list lies at or near the outer edge of the flat of keel, whose half-breadth takes the place of 12B\tfrac12 B. The flat of keel of the Series 60 ship extends 5.77 m to each side of the centreline amidships, so at 6.367 m a list of 1° adds 10.0 cm to the ship’s deepest draught, against 14.1 cm for a box of its breadth. That is nearly the 11 cm by which the Steel Flower was too deep. Wide ships are the most exposed, since a small list can put their bilge on the bottom4.

Under way in shallow water a ship sinks and trims as well. The water it pushes aside flows back faster beneath the bottom, and the fall in its pressure draws the ship down. This squat reduces the clearance under the keel below its static value2,4. Full forms usually squat most at the bow and fine forms at the stern4. Squat grows about as the square of the speed through the water and in proportion to the block coefficient4. A short-cut estimate of the greatest squat, from about 600 results measured on ships and models, is CBVk2/100C_B V_k^2/100 in metres in open water 1.1 to 1.4 times as deep as the draught, where VkV_k is the speed through the water in knots4. In a confined channel such as a river or a canal, where the immersed midship section of the ship takes 10 to 26.5 % of the cross-section of the channel, the estimate is twice as large4. For the Series 60 ship, with CBC_B = 0.60, at 6 knots (3.09 m/s) it gives 0.22 m in open water and 0.43 m in a channel. These exceed both the 15.4 cm gained by trimming and the 10.0 cm added by a 1° list, so the clearance that a ship needs under way has to allow for squat as well as for its static draught.

6.4.3 The Steel Flower

With the draught at F we can now return to the Steel Flower. On arrival at Port Colborne it was drawing 7.95 m aft and 8.11 m forward, a trim of 0.16 m by the head on a length of 222.48 m. The report does not give the ship’s centre of flotation, but Eq. (6.4) gives the draught at F for any position of F,

T(xF)=7.95+0.16xFL(m).T(x_F) = 7.95 + 0.16\,\frac{x_F}{L} \quad (\mathrm{m}) .

This is the draught at which the ship would have floated if the crew had made it exactly level by moving weight on board. It reaches 8.00 m only for xF/L=0.05/0.16=0.31x_F/L = 0.05/0.16 = 0.31, with F about 69.5 m forward of the after perpendicular, nearly a fifth of the length aft of amidships. The centre of flotation of a ship lies much nearer amidships than that, usually within about 3 % of the length5, and on the Series 60 hull 3 to 4 % aft. Even with F anywhere within 5 % of the length from amidships, the Steel Flower would have floated level at a draught between 8.022 m and 8.038 m (Fig. 6.6). It left the wharf drawing 8.02 m aft and 8.03 m forward, as level as the readings can show and within that range of draught. To reach 8.00 m, the ship would have had to lose 2.2 to 3.8 cm of draught at F. This would have meant discharging 2.2 to 3.8 times its tonnes per centimetre from over F, besides moving weight to keep it level. Unless the centre of flotation lay unusually far aft, moving weight on board could not have brought the ship to 8.00 m.

A graph of the draught at which the Steel Flower would float level against the position of its centre of flotation, given as a fraction of its length from the after perpendicular, from 0 to 1. A straight line rises from 7.95 m at 0 to 8.11 m at 1. A dotted horizontal line marks the Seaway maximum of 8.00 m; the sloping line crosses it at 0.31. A shaded vertical band between 0.45 and 0.55, labelled F within 5 % of the length from amidships, shows level draughts between 8.022 m and 8.038 m. A short horizontal bar across the band at 8.025 m marks the ship’s draught on leaving the wharf, when it drew 8.02 m aft and 8.03 m forward.

Figure 6.6 The draught at which the Steel Flower would have floated level, against the position of its centre of flotation, from the draughts on arrival at Port Colborne1.

6.5 Trim of a loading condition

6.5.1 From the weight table to the draughts

The methods of Secs. 6.2 and 6.3 change a known condition step by step. A loading condition can also be worked from the beginning. Its weight table gives the displacement Δm\Delta_m and the position of G, xGx_G and KG. The hydrostatic table, entered with the displacement, gives the draught at which the ship would float level, T(xF)T(x_F), and at that draught xBx_B, xFx_F and MCT 1 cm. If xGx_G equals xBx_B, the ship floats level at that draught, as the Series 60 ship does in its departure condition, with xG=xBx_G = x_B = 59.21 m at 7707 t. Otherwise G and B are a distance xG−xBx_G - x_B apart along the ship, the trimming moment is Δm(xG−xB)\Delta_m\,(x_G - x_B), and the ship trims about F until its centre of buoyancy lies on the vertical through G. In ship axes that vertical leans with the trim3. When the ship trims by the stern through an angle θ\theta (Fig. 6.7), the point of that vertical at the height of B lies (KG−KB)tanθ(\mathrm{KG} - \mathrm{KB})\tan\theta aft of G, while the centre of buoyancy moves aft from B, its position in the level ship, to B1\mathrm{B}_{1}, through BMLtanθ\mathrm{BM}_\mathrm{L}\tan\theta (Sec. 4.10.1). The two points coincide when

xB−BMLtanθ=xG−(KG−KB)tanθ,x_B - \mathrm{BM}_\mathrm{L}\tan\theta = x_G - (\mathrm{KG} - \mathrm{KB})\tan\theta ,

that is, when tanθ=(xB−xG)/GML\tan\theta = (x_B - x_G)/\mathrm{GM}_\mathrm{L}. With t=Ltanθt = L\tan\theta and ΔmGML=100LMCT1cm\Delta_m\,\mathrm{GM}_\mathrm{L} = 100\,L\,\mathrm{MCT\,1\,cm} from Eq. (4.22), the trim, in metres, is

t=Δm(xB−xG)100MCT1cm,(6.11)t = \frac{\Delta_m\,(x_B - x_G)}{100\,\mathrm{MCT\,1\,cm}} , \qquad (6.11)

by the stern when G lies aft of B2,4. The draughts at the ends follow from Eq. (6.4), TA=T(xF)+txF/LT_A = T(x_F) + t\,x_F/L and TF=TA−tT_F = T_A - t.

Two panels in rows. (a) The Series 60 hull in profile, drawn level in its own frame with heights three times as large as lengths, the after perpendicular at the left and the forward perpendicular at the right. The level waterline WL is dashed, and the trimmed waterline W1L1 is higher at the stern than at the bow. G lies a little below the waterlines and a little aft of amidships. A line through G, normal to W1L1 and leaning slightly forward as it rises, is labelled vertical through G. It meets the height of the centre of buoyancy at B1, a short distance aft of B, the centre of buoyancy of the ship floating level. A dashed box around G, B and B1 marks the region drawn in panel (b). (b) The region near B and G, enlarged and not to scale. B1 and B lie on a horizontal dashed line, B1 aft and B forward. The vertical through G rises from B1 through G and crosses a short segment of W1L1 at a right angle. A dotted line perpendicular to the keel runs down from G to the height of B, and the angle theta is marked between it and the vertical through G. Dimensions give KG minus KB, from the height of B up to G; (KG minus KB) tan theta, from B1 to the foot of the dotted line below G; and BM_L tan theta, from B1 to B. An arrow at the foot points forward.

Figure 6.7 B on the vertical through G in a ship trimmed by the stern: (a) the Series 60 ship, heights three times as large as lengths; (b) the construction near B and G, not to scale.

Because the vertical through G leans in ship axes, B1\mathrm{B}_{1} and G of a trimmed ship do not have the same xx. Before xBx_B taken from a program is compared with xGx_G, which is always measured in the ship, the axes of the program’s output are checked, since some programs give xBx_B in axes that stay level as the ship trims3.

Equation (6.11) can be turned round. When the draughts of a ship are read, T(xF)T(x_F) gives the displacement, and the trim gives the longitudinal position of G,

xG=xB−100MCT1cm⋅tΔm,(6.12)x_G = x_B - \frac{100\,\mathrm{MCT\,1\,cm}\cdot t}{\Delta_m} , \qquad (6.12)

which is how the longitudinal centre of gravity of a ship afloat is found from its draughts, for example in the inclining experiment2,6.

Example 6.7. The trim of the arrival condition. On arrival the Series 60 ship displaces 7236 t in sea water, with xGx_G = 60.22 m forward of the AP and KG = 6.13 m. Find the trim and draughts, using Table 6.1. Find the trim again with MCT 1 cm calculated with GML\mathrm{GM}_\mathrm{L}, taking KB = 3.24 m at this draught, and compare the two trims.

Show full solution

Solution.

The hydrostatic values. In the table, 7236 t lies 48.3/282.2=0.1748.3/282.2 = 0.17 of the way from 6.0 m to 6.2 m, so

T(xF)=6.034m,xB=59.39−0.17×0.10=59.37m,xF=57.02−0.17×0.34=56.96m,MCT1cm=82.75+0.17×2.32=83.14t⋅m/cm.\begin{aligned}T(x_F) &= 6.034\ \mathrm{m}, & x_B &= 59.39 - 0.17 \times 0.10 = 59.37\ \mathrm{m}, \\ x_F &= 57.02 - 0.17 \times 0.34 = 56.96\ \mathrm{m}, & \mathrm{MCT\,1\,cm} &= 82.75 + 0.17 \times 2.32 = 83.14\ \mathrm{t{\cdot}m/cm}.\end{aligned}

The trim. G lies 60.22−59.37=0.8560.22 - 59.37 = 0.85 m forward of B, so by Eq. (6.11)

t=7236×(59.37−60.22)100×83.14=−6150.68314=−0.740m,t = \frac{7236 \times (59.37 - 60.22)}{100 \times 83.14} = -\frac{6150.6}{8314} = -0.740\ \mathrm{m},

by the head.

The draughts. The ship trims about F, so

TA=6.034−0.740×56.96121.92=6.034−0.346=5.688m,TF=5.688+0.740=6.428m.\begin{aligned}T_A &= 6.034 - 0.740 \times \frac{56.96}{121.92} = 6.034 - 0.346 = 5.688\ \mathrm{m}, \\ T_F &= 5.688 + 0.740 = 6.428\ \mathrm{m}.\end{aligned}

MCT 1 cm with GML\mathrm{GM}_\mathrm{L}. Since MCT1cm≈ρIL/(100L)\mathrm{MCT\,1\,cm} \approx \rho\,I_L/(100\,L) by Eq. (4.23) and Δm=ρ∇\Delta_m = \rho\nabla, the value of Table 6.1 corresponds to BML=100LMCT1cm/Δm=100×121.92×83.14/7236=140.08\mathrm{BM}_\mathrm{L} = 100\,L\,\mathrm{MCT\,1\,cm}/\Delta_m = 100 \times 121.92 \times 83.14/7236 = 140.08 m. Then GML=3.24+140.08−6.13=137.19\mathrm{GM}_\mathrm{L} = 3.24 + 140.08 - 6.13 = 137.19 m, and by Eq. (4.22)

MCT1cm=7236×137.19100×121.92=81.42t⋅m/cm,\mathrm{MCT\,1\,cm} = \frac{7236 \times 137.19}{100 \times 121.92} = 81.42\ \mathrm{t{\cdot}m/cm},

which gives t=−6150.6/8142=−0.755t = -6150.6/8142 = -0.755 m.

Comment. Solved on the hull, the trim is 0.766 m by the head, with 5.674 m aft and 6.441 m forward; this is the condition whose draughts were read in Example 6.1. The trim from Table 6.1 is 2.6 cm short, and 1.5 cm of that comes from using BML\mathrm{BM}_\mathrm{L} in place of GML\mathrm{GM}_\mathrm{L}. The rest comes from the change of the waterplane as the ship trims, which Eq. (6.11) leaves out. In ship axes, B of the hull solution lies (6.13−3.24)×0.766/121.92=0.018(6.13 - 3.24) \times 0.766/121.92 = 0.018 m forward of G.

The loading conditions of the Series 60 ship are illustrative. In service, this arrival trim would be checked against the ship’s approved operating limits and the port’s requirements (Sec. 6.4). Water ballast taken into a tank aft could bring the ship towards even keel, with its effects on draught and stability checked as well.

6.5.2 Large changes of loading

Equations (6.5) to (6.11) rest on two approximations: that the trimmed waterline passes through the centre of flotation of the level waterline, and that MCT 1 cm does not change as the ship trims2. Both are good for small trims. As the trim grows, the immersed end and the emerged end are no longer wedges of the same shape, F moves along the waterplane, and the waterplane itself changes. Moore2 advises calculating the equilibrium directly from the hull when the draughts must be accurate, when the trim exceeds about 1/150 of the length, or when the trim changes the shape of the waterplane markedly. For the Series 60 ship, 1/150 of the length is 0.81 m. As can be seen from Fig. 6.8, at the departure displacement a trimming moment of 12,000 t·m trims the hull 1.44 m by the head, 6 cm more than Eq. (6.11) gives with the tabulated MCT 1 cm, but 1.38 m by the stern, within 1 cm of it. The two directions differ because the hull above and below the waterline is shaped differently at the bow and at the stern. With the hull trimmed 1.44 m by the head, F lies at 57.64 m and MCT 1 cm, computed as ρIL/(100L)\rho\,I_L/(100\,L) from the trimmed waterplane, is 82.4 t·m/cm. Trimmed 1.38 m by the stern, F lies at 55.48 m and MCT 1 cm is 90.7 t·m/cm, against 56.43 m and 86.9 t·m/cm level. As the trim grows, the ship therefore becomes easier to trim further by the head and harder to trim by the stern. The agreement within 1 cm by the stern is a coincidence. By the stern, MCT 1 cm grows with the trim, and this offsets the error of Table 6.1, whose MCT 1 cm, taken with BML\mathrm{BM}_\mathrm{L} in place of GML\mathrm{GM}_\mathrm{L}, is about 2 % too large.

Two graphs in rows for the Series 60 ship at its departure displacement mass of 7707 t, against the trimming moment from 20,000 t·m by the head on the left to 20,000 t·m by the stern on the right. (a) The trim, from 2.5 m by the head to 2.5 m by the stern. A solid curve gives the trim of the hull solved exactly; two straight lines give Equation (6.11), dashed with MCT 1 cm from Table 6.1 and dotted with MCT 1 cm calculated with GM_L. The three agree near zero. By the head the solid curve lies beyond both straight lines; by the stern it lies inside them. Two horizontal grey lines mark trims of 0.81 m, one 150th of the length, by the head and by the stern. (b) The trim of each straight line minus the trim of the hull, in centimetres. With MCT 1 cm from Table 6.1 the difference stays within 1 cm by the stern up to about 12,000 t·m, but grows to about 15 cm at 20,000 t·m by the head; with GM_L it grows on both sides, to about 10 cm by the head and 8 cm by the stern.

Figure 6.8 Trim of the Series 60 ship at its departure displacement against the trimming moment: (a) solved on the hull, and by Eq. (6.11) with two values of MCT 1 cm; (b) the error of the straight lines.

The incremental method of Sec. 6.3 makes a further approximation. It uses the hydrostatic values of the initial condition for the whole change, which fails when the displacement changes much, and it is acceptable only for small changes from a condition without a large initial trim2. Working from the weight table removes that error, because the hydrostatic values are those of the new displacement, but Eq. (6.11) still assumes a small trim.

When the Series 60 ship discharges all 4300 t of its cargo from the departure condition (Table 6.2), 3407 t remains, with xGx_G = 55.27 m and KG = 6.12 m. With the TPC, xFx_F and MCT 1 cm at the level draught of 6.366 m that Table 6.1 gives for the departure condition, the five holds give a sinkage of −4300/14.30=−300.7-4300/14.30 = -300.7 cm and a moment about F of 25,352 t·m. Equations (6.7) and (6.8) then give the first row of the table, with the aft draught 31 cm too deep. The hull at 3407 t has T(xF)T(x_F) = 3.139 m, xBx_B = 60.07 m, xFx_F = 59.95 m and MCT 1 cm = 63.74 t·m/cm. With these values, Eq. (6.11) gives a trim of 3407×(60.07−55.27)/6374=2.5663407 \times (60.07 - 55.27)/6374 = 2.566 m, within 2.3 cm of the hull at both ends, although the trim is 2.1 % of the length.

Table 6.2 Draughts of the Series 60 ship after discharging all its cargo from the departure condition, by three methods.

Method TAT_A (m) TFT_F (m) tt (m)
Incremental, with the hydrostatic values of the departure condition (Sec. 6.3) 4.710 1.792 2.918
From the weight table, Eq. (6.11) at 3407 t 4.401 1.835 2.566
Solved on the hull 4.399 1.812 2.587

When the trim itself is large, neither approximation can be relied on, and loading software finds the equilibrium of the hull directly. One method repeats the incremental step of Sec. 6.3 from the current waterline. At each step the hull is integrated below that waterline. The difference between the weight and the buoyancy, divided by TPC, then corrects the draught at F, and the difference between their moments about F, divided by MCT 1 cm, corrects the trim, both taken for that waterline2,3. For typical cases the iteration converges in about three steps2. A program must still check its force and moment residuals rather than stop after a fixed number of steps. Taken about F, the two corrections do not disturb each other to first order. A change of trim about F leaves the displaced volume unchanged, because the waterplane has no first moment about F, and a parallel sinkage adds a layer centred on F, which has no moment about F. This is also why a loaded mass was first placed over F in Sec. 6.3.1.

6.5.3 Exploring trim (Explorer 6.1)

In Explorer 6.1 you can float the Series 60 ship level at a displacement mass of your choice, then move a mass along its deck or load it at a chosen position. The new draughts are found in three ways: by the incremental method, from the new weight table with Eq. (6.11), and on the hull itself. The trim of the hull is compared with L/150L/150. For a mass moved on board the first two agree, because the displacement does not change. Try moving 200 t from the bow to the stern at the departure displacement, and then loading 600 t near the bow with the ship at 4000 t.

6.5.4 Displacement at a large trim

A large trim also affects the displacement found from the draughts. Equation (6.4) treats the waterplane as unchanged as the ship trims about F, and the volume brought in at one end then equals the volume taken out at the other. That is exact only for wall-sided ends. When the waterplane grows with the draught, as it does in most ships, the immersed end gains a little more volume than the emerged end loses. The first-order terms cancel about F, and what remains is of the second order in the trim angle. A strip of waterplane of breadth bb at a distance x−xFx - x_F from F is immersed by (xF−x)θ(x_F - x)\,\theta, and the extra volume from the flare of its sides is 12(∂b/∂z)(x−xF)2θ2\tfrac12\,(\partial b/\partial z)\,(x - x_F)^2\,\theta^2 per unit length. Summed over the waterplane, this is 12θ2dIL/dz\tfrac12\,\theta^2\,dI_L/dz, where ILI_L is the longitudinal second moment of the waterplane about F. With θ=t/L\theta = t/L and MCT1cm≈ρIL/(100L)\mathrm{MCT\,1\,cm} \approx \rho\,I_L/(100\,L), the extra displacement is

δΔm=50t2LdMCT1cmdz,(6.13)\delta\Delta_m = \frac{50\,t^2}{L}\,\frac{d\,\mathrm{MCT\,1\,cm}}{dz} , \qquad (6.13)

in tonnes, with tt and LL in metres and dMCT1cm/dzd\,\mathrm{MCT\,1\,cm}/dz the change of MCT 1 cm per metre of draught. It is always added when MCT 1 cm increases with the draught. In draught surveys it is called the second trim correction, with the change of MCT 1 cm taken over one metre of draught4,9. The derivation above evaluates that change at the draught at F, so here the metre is centred on it. For the arrival draughts of Example 6.1, a trim of 0.766 m by the head with the draught at F 6.032 m, Table 6.1 gives MCT 1 cm = 77.55 t·m/cm at 5.532 m and 88.57 t·m/cm at 6.532 m. The extra displacement is then

δΔm=50×0.7662121.92×11.02=2.7t,\delta\Delta_m = \frac{50 \times 0.766^2}{121.92} \times 11.02 = 2.7\ \mathrm{t},

so that the displacement mass from the marks becomes 7232.9+2.7=7235.67232.9 + 2.7 = 7235.6 t, against 7236 t in the weight table.

6.5.5 Change of trim with the density of the water

Section 3.5.2 showed that a ship moving from sea water into fresher water sinks, because its unchanged mass needs more volume. The extra volume is a thin layer at the waterline, and its centroid lies close to the centre of flotation. Unless F lies on the vertical through B, the layer moves B along the ship, while G does not move, so the ship also trims. With a layer of volume vv added to the volume ∇1\nabla_1, B moves through

δxB=v(xF−xB)∇1+v,(6.14)\delta x_B = \frac{v\,(x_F - x_B)}{\nabla_1 + v} , \qquad (6.14)

towards F, and the ship trims through

δt=ΔmδxB100MCT1cm(6.15)\delta t = \frac{\Delta_m\,\delta x_B}{100\,\mathrm{MCT\,1\,cm}} \qquad (6.15)

in metres, by the head when F lies aft of B, with MCT 1 cm taken in the new water4,5.

Predict 6.3. The Series 60 ship floats level in sea water with F 2.78 m aft of B. The ship moves into fresh water. Decide whether it will trim by the head or by the stern.

Check your prediction

Answer. By the head. The added layer is centred near F, aft of B, so B moves aft while G stays where it was, and the bow goes down until B is under G again. The change is 6.3 cm.

Example 6.8. From sea water into fresh water. In its departure condition the Series 60 ship displaces 7707 t, with xG=xBx_G = x_B = 59.21 m, and floats level in sea water at 6.366 m, the draught that Table 6.1 gives for this displacement. The ship moves up a river into fresh water of density 1.000 t/m³. Find the new draughts, using the table.

Show full solution

Solution.

The level draught in fresh water. The volume becomes 7707 m³, which in sea water would displace 1.025×7707=7899.71.025 \times 7707 = 7899.7 t. In the table this lies 0.503 of the way from 6.4 m to 6.6 m, so the ship would float level at 6.501 m, 0.135 m deeper.

The shift of B. The layer has a volume of 7707−7707/1.025=188.07707 - 7707/1.025 = 188.0 m³, centred near F at the mid-depth of the layer, 6.43 m, where xF=56.34x_F = 56.34 m. By Eq. (6.14), B moves through

δxB=188.0×(56.34−59.21)7707=−0.070m,\delta x_B = \frac{188.0 \times (56.34 - 59.21)}{7707} = -0.070\ \mathrm{m},

that is, 0.070 m aft.

The change of trim. At 6.501 m MCT 1 cm is 88.26 t·m/cm in sea water, and 88.26/1.025=86.1188.26/1.025 = 86.11 t·m/cm in fresh water, so

δt=7707×(−0.070)100×86.11=−0.063m,\delta t = \frac{7707 \times (-0.070)}{100 \times 86.11} = -0.063\ \mathrm{m},

by the head.

The draughts. At 6.501 m, xFx_F = 56.25 m, so TA=6.501−0.063×56.25/121.92=6.472T_A = 6.501 - 0.063 \times 56.25/121.92 = 6.472 m and TF=6.472+0.063=6.535T_F = 6.472 + 0.063 = 6.535 m.

Comment. Solved on the hull, the draughts in fresh water are 6.472 m aft and 6.535 m forward. The trim is small, but it adds to the sinkage at the bow, which is where a ship trimmed by the head meets a draught limit.

6.5.6 Trim calculator (Calculator 6.1)

Calculator 6.1 finds the draughts of the Series 60 ship after loading, discharging and moving masses, starting from its draughts at the perpendiculars. It works the change by the incremental method of Sec. 6.3, with TPC, xFx_F and MCT 1 cm read at the initial draught at F or at a draught you choose, and MCT 1 cm is that of Table 6.1, ρIL/(100L)\rho\,I_L/(100\,L). For comparison, the new condition is also worked from the weight table: the displacement and xGx_G are found from the initial draughts by Eqs. (6.4) and (6.12), the masses are added, and the trim follows from Eq. (6.11). A difference of more than 3 cm at an end triggers a prompt to examine the approximations. This is a teaching threshold, not an accuracy tolerance; agreement between two approximations does not establish their accuracy. The locked presets repeat three of the worked examples, and “Your own loading” accepts any list of masses. A change that would take the displacement outside Table 6.1, or either end draught below the keel or above the deck, is refused.

6.6 Longitudinal stability

6.6.1 The longitudinal metacentric height in service

Section 4.10.1 showed that the longitudinal metacentric radius of a ship is of the order of its length. For the Series 60 ship in its departure condition, GML\mathrm{GM}_\mathrm{L} is 135.0 m, against a transverse GM of 0.659 m, both without the free surfaces. A moment of mass of 88.6 t·m heels the ship through 1°. Applied as a trimming moment, it changes the trim by 1.04 cm, an angle of 0.0049°, since the ship’s MCT 1 cm by Eq. (4.22) is 85.3 t·m/cm. An intact ship of ordinary form has a large initial restoring margin in pitch in calm water. The practical hydrostatic question is usually its draughts and trim under the moments that act on it2,6.

Like the transverse GM, the longitudinal metacentric height can be measured on the ship, by moving a known mass mm a distance dd along the ship and reading the change of trim, δt\delta t, that it causes4. By Eq. (6.5) with MCT 1 cm from Eq. (4.22),

GML=mdLΔmδt,(6.16)\mathrm{GM}_\mathrm{L} = \frac{m\,d\,L}{\Delta_m\,\delta t} , \qquad (6.16)

with δt\delta t in metres. In practice the trim is used the other way round, to find xGx_G from the draughts by Eq. (6.12).

6.6.2 Free surface and trim

A slack tank reduces the longitudinal stability as it reduces the transverse stability. The argument of Sec. 5.3.1, with the tank inclined along its length instead of across it, gives a virtual rise of G of

GGv,L=∑ρliLΔm,(6.17)\mathrm{GG}_{v,L} = \frac{\sum \rho_l\,i_L}{\Delta_m} , \qquad (6.17)

where ρl\rho_l is the density of the liquid in the tank and iL=bl3/12i_L = b\,l^3/12 is the second moment of the free surface of a rectangular tank of length ll and breadth bb about its transverse axis. The correction has the form of the transverse free surface correction, but it is measured against GML\mathrm{GM}_\mathrm{L}, which is of the order of the length. For the starboard fuel tank FO3S of the Series 60 ship, the rectangular tank of Table 5.1, 23.2 m long and 6.9 m wide, iL=6.9×23.23/12=7180.1i_L = 6.9 \times 23.2^3/12 = 7180.1 m⁴, and with fuel of density 0.98 t/m³ the virtual rise is 0.98×7180.1/7707=0.9130.98 \times 7180.1/7707 = 0.913 m. That is 0.68 % of the departure GML\mathrm{GM}_\mathrm{L} of 135.0 m, and it reduces MCT 1 cm by that fraction, whereas FO3S takes 12 % of the transverse GM. The value of iLi_L holds only while the surface stays clear of the top and the bottom of the tank. In a tank of length ll and depth hth_t, filled to a fraction ff of its depth, the surface reaches the top when tanθ=2ht(1−f)/l\tan\theta = 2\,h_t\,(1 - f)/l. FO3S holds 175 t of its 191.4 t at departure, so ff = 0.914, tanθ=2×1.22×0.086/23.2\tan\theta = 2 \times 1.22 \times 0.086/23.2, and its surface reaches the top of the tank at a trim of about 1.10 m. For ships with normal tankage the effect on trim is small and usually ignored. It matters in vessels without extensive transverse subdivision, such as some river barges, and in ships with large damaged spaces2.

6.6.3 Loss of longitudinal stability

A ship comes near the limit of its longitudinal stability only when much of the waterplane is lost or when the ship is supported at one point. A compartment at one end that floods removes waterplane far from F, where it contributes most to ILI_L, and also adds a large trimming moment. A ship touching the bottom or a dock block at one end is supported there, and its stability then depends on the reaction at the support. In some unusual forms, among them catamarans and offshore platforms, the longitudinal stability need not exceed the transverse by a wide margin, and each such design is assessed on its own6. A catamaran’s separated hulls greatly increase its transverse waterplane moment. Their separation does not give the same increase in the longitudinal moment; the longitudinal stability must be calculated from the actual hull geometry and loading10. Trim also changes as a ship heels, because B moves along the ship as well as across, and stability calculations at large angles allow for this.

The signs, units and conditions of the main relations of Secs. 6.1 to 6.5 are listed in Table 6.3.

Table 6.3 Signs, units and conditions of the main relations of trim in Secs. 6.1 to 6.5.

Quantity or relation Sign and unit Condition
Trim, t=TA−TFt = T_A - T_F (Sec. 6.1.1) m, positive by the stern draughts at the perpendiculars; mark readings reduced by Eqs. (6.2) and (6.3)
Trim angle, tanθ=t/L\tan\theta = t/L (Sec. 6.1.1) the sign of tt LL between perpendiculars; trim is stated as tt, not as θ\theta
Draught at xx, Eq. (6.1) m, xx forward of the AP a straight hull, neither hogged nor sagged
Draught at F, Eq. (6.4) m; gives the displacement exact for a straight waterline; the displacement read at it needs a small trim; at larger trims, add Eq. (6.13)
xFx_F, with TPC and MCT 1 cm (Sec. 6.3.1) m, measured forward of the AP read at the draught at F; for a large mass, midway between the initial and final draughts
MCT 1 cm, from Eq. (4.23) t·m/cm; other tables may give the moment to change trim one metre, or a moment of force BML\mathrm{BM}_\mathrm{L} in place of GML\mathrm{GM}_\mathrm{L}, which makes it about 2 % too large for the Series 60 ship (Sec. 6.1.3)
Mass moved, Eq. (6.5) cm; by the head (negative) for a mass moved forward small trim (Sec. 6.5.2)
End draughts, Eq. (6.6) cm, opposite in sign; δTA−δTF\delta T_A - \delta T_F equals δt\delta t the waterline turns about F; equal shares only when F lies amidships
Mass loaded, Eqs. (6.7) and (6.8) cm; by the stern for a mass aft of F; a mass discharged is negative small mass, otherwise the values midway through the change (Sec. 6.3.1)
Trim of a loading condition, Eq. (6.11) m, by the stern when G lies aft of B small trim, values at the new displacement; a solution on the hull beyond about L/150L/150 (Sec. 6.5.2)

6.7 Trim in industry today

This section describes practice in 2026.

Loading computers. Stability instruments approved under Part B of the International Code on Intact Stability, 2008 (IS Code) present, for each loading condition, the trim and list and the draughts at the draught marks and at the perpendiculars11. To approve an instrument, the Administration is given the positions of the perpendiculars and, if appropriate, the method used to derive the draughts at the actual positions of the marks11. The Code recommends that the hydrostatic and stability curves be prepared for the range of trim of the operating loading conditions, taking into account the change of trim with heel, that is, with the trim free11. Among the contents it recommends for the stability booklet are hydrostatic curves or tables and cross curves of stability calculated on a free-trimming basis, for the ranges of displacement and trim expected in normal operation11. Where curves of limiting GM are used, the IS Code requires them to cover the full range of operational trims, unless the Administration agrees that the effect of trim is not significant11. Modern software finds the equilibrium of the hull directly, with the properties of the hull computed for the trimmed waterline instead of read from an even-keel table2. Such a program is approved against the tolerances of the IMO guidelines MSC.1/Circ.1229 and of IACS UR L5 (Sec. 2.10.2). For the draughts, compared with those of the approved stability information or of the approving authority’s model, the Circular prints the tolerance as 1 % / 5 cm max12. UR L5 gives the same two values and allows the greater of them13, which for the Series 60 ship is 6 cm at about 6 m, and 5 cm at any draught up to 5 m. After the discharge of Table 6.2, the draughts given by Eq. (6.11) at the new displacement are within that tolerance, but those of the incremental method are not.

Draught limits. On the St. Lawrence Seaway14 the maximum draught in both the Montreal to Lake Ontario section and the Welland Canal is 8.08 m in 2026, 8 cm more than the limit the Steel Flower faced in 1996. Ships with a draught information system approved by a member of IACS may be allowed 7 cm more under the Seaway Handbook15. The Seaway also refuses ships trimmed by the stern more than 4.57 m without special permission15. The Panama Canal Authority applies its maximum transit draught to the deepest point of the ship in tropical fresh water. Its notice to shipping of 2026 warns that the passage into the fresh water of the canal often trims large ships 7.5 to 10 cm by the head16, the effect calculated in Example 6.8. Ports also limit trim for safe handling. The Port of Port Hedland, for example, sets a minimum forward draught and a maximum trim by the stern for ships arriving at its berths, such as 0.7 % of the length overall for ships of more than 80,000 tonnes deadweight17.

Draught surveys. The reduction of mark readings to the perpendiculars and the first and second trim corrections of Secs. 6.1.3 and 6.5.4 are standard steps of a draught survey. Wawrzyński9 compared the usual second trim correction with the displacement computed directly from the hull of a bulk carrier 176.65 m long. The errors stayed below 0.5 times the TPC up to a trim of 3 m, but at a trim of 6 m by the stern they spread over nearly 5 times the TPC. He recommended that shipyards supply tables of second trim corrections computed from the hull.

Bow height. The International Convention on Load Lines sets a minimum bow height, measured at the forward perpendicular from the waterline of the summer freeboard at the designed trim18. Trim enters the rules for that reason as well as through the draught. In 2009 the Norwegian general cargo ship Langeland foundered in rough weather in the Kosterfjord off the west coast of Sweden, with the loss of all six crew. The investigators found that the ship’s stability calculations had not taken account of trim, and that it had too little reserve buoyancy forward. Requirements on the maximum trim by the head and the minimum bow height of a fully loaded ship had applied when the Langeland was built in 1971 and were removed in 1987, and the investigators recommended that they be reintroduced19.

Trim and fuel. The guidelines of the International Maritime Organization for the Ship Energy Efficiency Management Plan, adopted by resolution MEPC.395(82), state that for any draught there is a trim that gives the least resistance. They advise that trim and ballast be planned with this in mind where design and safety allow20. Model tests and computations of fluid flow on the KRISO container ship21 found that a trim of 0.25° by the head reduced the calm-water resistance at the design draught by 1.25 %, while a trim of 1° by the stern increased it by about 8 %. The best trim changes with the speed22, and it has to be found again for shallow water, where the flow round the hull is different23. Trim optimization is therefore offered as a service. FORCE Technology, for example, describes computations of the flow round a ship in 120 to 180 combinations of draught, trim and speed, from which the best trim for a voyage is chosen on board24. Any trim chosen for fuel must still meet the limits on stability, strength and draught.

6.8 From trim to the hydrostatic curves

Every method of this chapter needed the hydrostatic values of the ship at its draught: the displacement, TPC, the centres of buoyancy and flotation, and MCT 1 cm. Table 6.1 gave a few of them at intervals of 0.2 m. On board, and in the design office, they are drawn as curves against the draught, together with KB, KM, KML\mathrm{KM}_\mathrm{L} and the coefficients of form, so that any of them can be read at any draught. In Chapter 7 we will see how these hydrostatic curves are calculated from the lines of the hull and how each of them varies with the draught. We will also return to the Bonjean curves of Chapter 1, which give the displacement of a ship at a trim too large for the level curves to be trusted.

Summary

Notes on the data

The Steel Flower. The ship’s length, cargo, draughts, the Seaway limit of 1996, the events in the canal and the damage are from the report of the Transportation Safety Board of Canada1. The report gives neither the ship’s hydrostatic data nor where its draughts were read. The length of 222.48 m is taken as the length between perpendiculars and the draughts as those at the perpendiculars; only xF/Lx_F/L affects the conclusion. The band of 5 % of the length for F is an assumption, wider than the 3 % usually taken5.

Table 6.1 and the hull solutions. The hydrostatic values are computed on the Series 60 surface by scripts/ch06_data.py, with MCT 1 cm from ρIL/(100L)\rho\,I_L/(100\,L). “Solved on the hull” means that the equilibrium of the trimmed hull is found by direct integration of its sections below the inclined waterline, adjusting the draught and trim until the displaced mass equals the displacement and B lies on the normal to the waterline through G, without the small-trim approximations of this chapter; the method is that of Chapter 3 (ch03/scripts/inclined.py). The centre of flotation and MCT 1 cm of the trimmed hull in Sec. 6.5.2 are integrated over its inclined waterplane at the solved equilibrium. The cargo holds are those of Table 3.1, and the arrival condition is that of Exercise 3.10.

The examples. The positions of the draught marks, the thickness of the keel plate, the cargo moved, loaded and discharged, the lock of Example 6.6 and the projections below the keel in Sec. 6.4.2 are illustrative; the Series 60 hull has no projections. The half-breadth of its flat of keel, 5.77 m, is that of the surface at the baseline amidships, and the deepest draught of the listed hull is computed on the surface by scripts/ch06_data.py. A mass moved on deck at the departure or arrival displacement is taken as part of that displacement, although those loading conditions carry no deck cargo. In Examples 6.5 and 6.6 the ship’s condition is given only by the draughts; for the hull solutions it is taken as the displacement and xGx_G at which the hull floats at those draughts, with KG = 6.0 m. The printouts of Exercise 6.10 give the hull solution, with the deck cargo 11.0 m above the keel, and the hydrostatic values of Table 6.1 at the displacement.

Figure 6.7. Panel (a) is the frame of Animation 6.1 in which 200 t has moved from 100 m to 20 m forward of the AP at the departure displacement, solved on the hull. In that condition (KG−KB)tanθ(\mathrm{KG} - \mathrm{KB})\tan\theta is 0.037 m and BMLtanθ\mathrm{BM}_\mathrm{L}\tan\theta is 2.06 m, a ratio of about 1 to 56, which panel (b) draws as about 1 to 4.

Explorer 6.1 and Animation 6.1. The explorer interpolates draughts solved on the hull for displacements from 3000 t to 9000 t and xGx_G from 50 m to 70 m, with KG = 6.0 m; combinations at which the deck edge would go under or the keel come out of the water are not offered. The animation starts from the displacement and centre of gravity of the departure condition of Table 3.1, with 200 t of that displacement on the deck at 100 m from the AP, and solves the hull for each position of the mass.

Exercises

Under each exercise, “Show answers” opens its short answers and “Show full solution” its worked solution. Unless stated otherwise the water is sea water of density 1.025 t/m³ and the draughts are moulded draughts at the perpendiculars.

6.1 A box barge 80.00 m long has its aft draught marks 1.50 m forward of the AP and its forward marks 2.00 m aft of the FP. The marks read keel draughts of 3.42 m aft and 2.86 m forward, and the keel plate is 15 mm thick. Find the moulded draughts at the perpendiculars and the trim.

Show answers

3.416 m aft; 2.830 m forward; 0.586 m by the stern

Show full solution

The trim. The marks are 80.00−1.50−2.00=76.5080.00 - 1.50 - 2.00 = 76.50 m apart, so

t=(3.42−2.86)×80.0076.50=0.56×1.0458=0.586m,t = (3.42 - 2.86) \times \frac{80.00}{76.50} = 0.56 \times 1.0458 = 0.586\ \mathrm{m},

by the stern.

The draughts. The keel draughts at the perpendiculars are

TA=3.42+0.586×1.5080.00=3.42+0.011=3.431m,TF=3.431−0.586=2.845m,\begin{aligned}T_A &= 3.42 + 0.586 \times \frac{1.50}{80.00} = 3.42 + 0.011 = 3.431\ \mathrm{m}, \\ T_F &= 3.431 - 0.586 = 2.845\ \mathrm{m},\end{aligned}

and the moulded draughts, 0.015 m less, are 3.416 m aft and 2.830 m forward.

6.2 The Series 60 ship floats at 6.60 m aft and 6.20 m forward. Find the draught at the centre of flotation and the displacement mass, using Table 6.1, and its error if the mean of the end draughts were used instead.

Show answers

6.415 m; 7776.5 t; 21.6 t too little

Show full solution

The draught at F. The mean of the end draughts is 6.40 m, where xFx_F = 56.38 m. With tt = 0.40 m,

T(xF)=6.60−0.40×56.38121.92=6.60−0.185=6.415m.T(x_F) = 6.60 - 0.40 \times \frac{56.38}{121.92} = 6.60 - 0.185 = 6.415\ \mathrm{m}.

The displacement. 6.415 m lies 0.075 of the way from 6.4 m to 6.6 m, so

Δm=7754.9+0.075×287.6=7776.5t.\Delta_m = 7754.9 + 0.075 \times 287.6 = 7776.5\ \mathrm{t}.

At the mean draught, 6.40 m, the table gives 7754.9 t, 21.6 t too little. F lies aft of amidships and the ship trims by the stern, so the mean of the end draughts is less than the draught at F.

6.3 On arrival the Series 60 ship floats at 5.674 m aft and 6.440 m forward, with its draught at F 6.032 m, where Table 6.1 gives MCT 1 cm = 83.12 t·m/cm. Find the mass of deck cargo that must be moved aft, from 91.28 m to 20.90 m forward of the AP, to bring the ship to even keel, and the draught at which it then floats.

Show answers

90.5 t; 6.032 m

Show full solution

The change of trim. The ship trims 0.766 m by the head, so the trim must change by 76.6 cm by the stern. The moment needed is 76.6×83.12=6367.076.6 \times 83.12 = 6367.0 t·m.

The mass. The mass moves 91.28−20.90=70.3891.28 - 20.90 = 70.38 m aft, so

m=6367.070.38=90.5t.m = \frac{6367.0}{70.38} = 90.5\ \mathrm{t}.

The draught. Moving a mass on board does not change the draught at F, so the ship floats level at 6.032 m. Solved on the hull, the ship floats at 6.048 m aft and 6.019 m forward after the move, a trim of 3 cm left by the approximations of Sec. 6.5.2.

6.4 A box barge 72 m long and 14 m wide floats level at a draught of 3.2 m, with MCT 1 cm = 60.0 t·m/cm found from its GML\mathrm{GM}_\mathrm{L}. (a) 40 t on its deck is moved 36 m aft. Find the new draughts. (b) Starting again from the level condition, find where 50 t must be loaded to leave the aft draught unchanged, and the forward draught after loading it.

Show answers

(a) 3.320 m aft, 3.080 m forward; (b) 11.62 m forward of amidships, 3.297 m forward

Show full solution

(a) The shift. The trim changes by 40×36/60.0=24.0040 \times 36/60.0 = 24.00 cm by the stern. For a box F lies amidships, so each end moves by half of it, 12.00 cm, and the draughts become 3.320 m aft and 3.080 m forward.

(b) The constant aft draught. The waterplane is 72×14=100872 \times 14 = 1008 m², so TPC = 1.025×1008/100=10.331.025 \times 1008/100 = 10.33 t/cm. With xFx_F = 36 m, Eq. (6.9) with x0=0x_0 = 0 gives

x−xF=60.0×7210.33×36=4320371.88=11.62mx - x_F = \frac{60.0 \times 72}{10.33 \times 36} = \frac{4320}{371.88} = 11.62\ \mathrm{m}

forward of amidships. The change of trim is 50×(−11.62)/60.0=−9.6850 \times (-11.62)/60.0 = -9.68 cm, and since the aft draught does not change, the forward draught increases by 9.68 cm, to 3.297 m.

6.5 The Wigley hull, 100 m long and 10 m wide, floats level at 6.25 m. Its waterplane, y=(B/2)(1−ξ2)y = (B/2)(1 - \xi^2) with ξ=2x/L−1\xi = 2x/L - 1, has an area of 666.67 m² and a second moment of L3B/30=333,333L^3B/30 = 333{,}333 m⁴ about its centroid amidships. (a) Find TPC, and MCT 1 cm from ρIL/(100L)\rho\,I_L/(100\,L). (b) 60 t is loaded 20 m forward of amidships. Find the new draughts.

Show answers

(a) 6.83 t/cm, 34.17 t·m/cm; (b) 6.162 m aft, 6.513 m forward

Show full solution

(a) TPC and MCT 1 cm.

TPC=1.025×666.67100=6.83t/cm,MCT1cm=1.025×333,333100×100=34.17t⋅m/cm.\mathrm{TPC} = \frac{1.025 \times 666.67}{100} = 6.83\ \mathrm{t/cm}, \qquad \mathrm{MCT\,1\,cm} = \frac{1.025 \times 333{,}333}{100 \times 100} = 34.17\ \mathrm{t{\cdot}m/cm}.

(b) The loading. The sinkage is 60/6.83=8.7860/6.83 = 8.78 cm. The mass is 20 m forward of F, which lies amidships, so

δt=60×(−20)34.17=−35.12cm.\delta t = \frac{60 \times (-20)}{34.17} = -35.12\ \mathrm{cm}.

Each end moves by half the change of trim, 17.56 cm, so δTA=8.78−17.56=−8.78\delta T_A = 8.78 - 17.56 = -8.78 cm and δTF=8.78+17.56=26.34\delta T_F = 8.78 + 17.56 = 26.34 cm. The draughts are 6.162 m aft and 6.513 m forward.

6.6 The Series 60 ship floats level at 6.366 m, where TPC = 14.30 t/cm, xFx_F = 56.43 m and MCT 1 cm = 86.87 t·m/cm. At an intermediate port the ship discharges 120 t from hold 1, centred 105.68 m forward of the AP, and 90 t from hold 4, centred 56.03 m forward of the AP, and loads 150 t of deck cargo centred 75.00 m forward of the AP. Find the new draughts.

Show answers

6.489 m aft; 6.133 m forward

Show full solution

The sinkage. The net mass is −120−90+150=−60-120 - 90 + 150 = -60 t, so the ship rises by 60/14.30=4.260/14.30 = 4.2 cm.

The moments about F. With xFx_F = 56.43 m, each mass contributes m(xF−x)m\,(x_F - x):

Item mm (t) xx (m) xF−xx_F - x (m) m(xF−x)m\,(x_F - x) (t·m)
Hold 1, discharged −120 105.68 −49.25 5910.0
Hold 4, discharged −90 56.03 0.40 −36.0
Deck cargo, loaded 150 75.00 −18.57 −2785.5
Total −60 3088.5

so the trim changes by 3088.5/86.87=35.63088.5/86.87 = 35.6 cm by the stern.

The draughts. The ends change by

δTA=−4.2+35.6×56.43121.92=−4.2+16.5=12.3cm,δTF=−4.2−35.6×65.49121.92=−4.2−19.1=−23.3cm,\begin{aligned}\delta T_A &= -4.2 + 35.6 \times \frac{56.43}{121.92} = -4.2 + 16.5 = 12.3\ \mathrm{cm}, \\ \delta T_F &= -4.2 - 35.6 \times \frac{65.49}{121.92} = -4.2 - 19.1 = -23.3\ \mathrm{cm},\end{aligned}

so the draughts are 6.489 m aft and 6.133 m forward.

6.7 The Series 60 ship floats level at 6.366 m, where TPC = 14.30 t/cm, xFx_F = 56.43 m and MCT 1 cm = 86.87 t·m/cm. Find where 80 t must be loaded to leave the forward draught unchanged, and the aft draught after loading it.

Show answers

45.12 m forward of the AP; 6.470 m

Show full solution

By Eq. (6.9) with x0=Lx_0 = L,

xF−x=86.87×121.9214.30×65.49=10,591.2936.5=11.31m,x_F - x = \frac{86.87 \times 121.92}{14.30 \times 65.49} = \frac{10{,}591.2}{936.5} = 11.31\ \mathrm{m},

so the mass goes 11.31 m aft of F, at x=56.43−11.31=45.12x = 56.43 - 11.31 = 45.12 m. The change of trim is 80×11.31/86.87=10.4280 \times 11.31/86.87 = 10.42 cm by the stern, and since the forward draught does not change, the aft draught increases by 10.42 cm, to 6.470 m.

6.8 A ship 91.44 m between perpendiculars floats at 3.734 m forward and 4.420 m aft. Its TPC is 8.00 t/cm, the centre of flotation is 3.66 m aft of amidships and MCT 1 cm is 36.58 t·m/cm. Find where a mass of 60.96 t must be placed for the ship to float level, and its draught then. (Adapted from Attwood7.)

Show answers

37.50 m forward of amidships; 4.181 m

Show full solution

The change of trim. The trim is 4.420−3.734=0.6864.420 - 3.734 = 0.686 m by the stern, so the trim must change by 68.6 cm by the head, which needs a moment of 36.58×68.6=2509.436.58 \times 68.6 = 2509.4 t·m.

The position. The mass must lie 2509.4/60.96=41.162509.4/60.96 = 41.16 m forward of F. F lies 3.66 m aft of amidships, so the mass goes 41.16−3.66=37.5041.16 - 3.66 = 37.50 m forward of amidships.

The draught. F lies 45.72−3.66=42.0645.72 - 3.66 = 42.06 m forward of the AP, so the draught at F is 4.420−0.686×42.06/91.44=4.420−0.3155=4.10454.420 - 0.686 \times 42.06/91.44 = 4.420 - 0.3155 = 4.1045 m. The mass sinks the ship by 60.96/8.00=7.6260.96/8.00 = 7.62 cm, and the ship floats level at 4.1045+0.0762=4.1814.1045 + 0.0762 = 4.181 m.

6.9 A bulk carrier 180 m between perpendiculars floats in fresh water at 9.30 m aft and 9.62 m forward. Its centre of flotation is 86.0 m forward of the AP and its TPC in fresh water is 38.5 t/cm. A waterway admits no ship drawing more than 9.40 m. (a) Find the draught at F, and decide whether moving ballast on board can bring the ship within the limit. (b) Find the least mass that must be discharged.

Show answers

(a) 9.453 m, no; (b) 204 t

Show full solution

(a) The draught at F. The trim is 0.32 m by the head, t=−0.32t = -0.32 m, so

T(xF)=9.30+0.32×86.0180=9.30+0.153=9.453m.T(x_F) = 9.30 + 0.32 \times \frac{86.0}{180} = 9.30 + 0.153 = 9.453\ \mathrm{m}.

This exceeds 9.40 m, so moving ballast on board cannot bring both ends within the limit.

(b) The least discharge. The draught at F must fall by 0.053 m, so at least 100×38.5×0.053=204100 \times 38.5 \times 0.053 = 204 t must come off, taken from over F, with ballast moved to bring the ship level.

6.10 The Series 60 ship in its departure condition displaces 7707 t, with xGx_G = 59.207 m. The ship loads 195 t of deck cargo centred 40.00 m forward of the AP, which brings it to 7902 t, its summer displacement mass. The stability instrument on board then prints an LCG (xGx_G) of 58.733 m, an LCB (xBx_B) of 59.139 m, both forward of the AP, and a KG of 6.013 m. It also prints a draught of 6.502 m at the centre of flotation, draughts of 6.671 m at the AP and 6.304 m at the FP, and a trim of 0.367 m by the stern. (a) Check the LCG, and check the trim and the draughts at the perpendiculars with Eq. (6.11), using Table 6.1 and interpolating xBx_B to three decimals. (b) A second program prints an LCB of 58.725 m and a KB of 3.492 m for this condition. Explain why its LCB differs from the first, and why it cannot be used in Eq. (6.11).

Show answers

(a) 0.363 m by the stern, 6.669 m aft, 6.306 m forward; (b) it is B of the trimmed ship in ship axes, 0.008 m aft of G

Show full solution

(a) The centre of gravity. By moments about the AP,

xG=7707×59.207+195×40.007902=456,308.3+78007902=58.733m,x_G = \frac{7707 \times 59.207 + 195 \times 40.00}{7902} = \frac{456{,}308.3 + 7800}{7902} = 58.733\ \mathrm{m},

as printed.

The hydrostatic values. 7902 t lies 147.1/287.6=0.51147.1/287.6 = 0.51 of the way from 6.4 m to 6.6 m in Table 6.1, so

T(xF)=6.502m,xB=59.19−0.51×0.10=59.139m,xF=56.38−0.51×0.25=56.25m,MCT1cm=87.24+0.51×2.02=88.27t⋅m/cm.\begin{aligned}T(x_F) &= 6.502\ \mathrm{m}, & x_B &= 59.19 - 0.51 \times 0.10 = 59.139\ \mathrm{m}, \\ x_F &= 56.38 - 0.51 \times 0.25 = 56.25\ \mathrm{m}, & \mathrm{MCT\,1\,cm} &= 87.24 + 0.51 \times 2.02 = 88.27\ \mathrm{t{\cdot}m/cm}.\end{aligned}

The printed LCB and draught at the centre of flotation agree with them.

The trim. By Eq. (6.11),

t=7902×(59.139−58.733)100×88.27=3208.28827=0.363m,t = \frac{7902 \times (59.139 - 58.733)}{100 \times 88.27} = \frac{3208.2}{8827} = 0.363\ \mathrm{m},

by the stern.

The draughts. TA=6.502+0.363×56.25/121.92=6.502+0.167=6.669T_A = 6.502 + 0.363 \times 56.25/121.92 = 6.502 + 0.167 = 6.669 m and TF=6.669−0.363=6.306T_F = 6.669 - 0.363 = 6.306 m. They agree with the printout to 2 mm at both ends, far inside the draught tolerance of Sec. 6.7.

(b) The second LCB. In ship axes the vertical through G leans with the trim (Fig. 6.7). With the ship trimmed 0.367 m by the stern, the point of that vertical at the height of B lies

(KG−KB)tL=(6.013−3.492)×0.367121.92=0.008m(\mathrm{KG} - \mathrm{KB})\,\frac{t}{L} = (6.013 - 3.492) \times \frac{0.367}{121.92} = 0.008\ \mathrm{m}

aft of G, at 58.733−0.008=58.72558.733 - 0.008 = 58.725 m. The second program therefore gives the position of B in the trimmed ship, in ship axes, where B lies on the vertical through G as equilibrium requires. The first gives xBx_B of the ship floating level at its displacement. Equation (6.11) needs that level value, because the trim arises from the distance between G and B of the level ship. With the second value it would give 7902×(58.725−58.733)/8827=−0.0077902 \times (58.725 - 58.733)/8827 = -0.007 m, a ship nearly level, against the printed trim of 0.367 m. Before an LCB from a program is used, the axes and the waterline to which it refers are checked.

Comment. The printed trim is 4 mm larger than that of Eq. (6.11), because the instrument finds the equilibrium of the hull itself. Two effects of opposite sign are at work. MCT 1 cm of Table 6.1 takes BML\mathrm{BM}_\mathrm{L} in place of GML\mathrm{GM}_\mathrm{L}: here BML=100×121.92×88.27/7902=136.19\mathrm{BM}_\mathrm{L} = 100 \times 121.92 \times 88.27/7902 = 136.19 m, and at this precision KB is 3.49 m both for the ship level at 6.502 m and for the trimmed ship, so GML=3.49+136.19−6.013=133.67\mathrm{GM}_\mathrm{L} = 3.49 + 136.19 - 6.013 = 133.67 m. With GML\mathrm{GM}_\mathrm{L} the trim becomes 0.363×136.19/133.67=0.3700.363 \times 136.19/133.67 = 0.370 m, which is 3 mm beyond the printed 0.367 m. The correction overshoots because by the stern MCT 1 cm grows with the trim (Sec. 6.5.2), and this stiffening takes back part of what GML\mathrm{GM}_\mathrm{L} adds.

6.11 The Series 60 ship floats at 6.52 m aft and 6.21 m forward. Find the displacement mass and the longitudinal position of the centre of gravity, using Table 6.1.

Show answers

7722.1 t; 58.85 m forward of the AP

Show full solution

The draught at F. The mean of the end draughts is 6.365 m, where xF=56.68−0.825×0.30=56.43x_F = 56.68 - 0.825 \times 0.30 = 56.43 m. The trim is 0.31 m by the stern, so

T(xF)=6.52−0.31×56.43121.92=6.52−0.143=6.377m.T(x_F) = 6.52 - 0.31 \times \frac{56.43}{121.92} = 6.52 - 0.143 = 6.377\ \mathrm{m}.

The hydrostatic values. 6.377 m lies 0.885 of the way from 6.2 m to 6.4 m, so

Δm=7469.9+0.885×285.0=7722.1t,xB=59.20m,MCT1cm=86.99t⋅m/cm.\Delta_m = 7469.9 + 0.885 \times 285.0 = 7722.1\ \mathrm{t}, \qquad x_B = 59.20\ \mathrm{m}, \qquad \mathrm{MCT\,1\,cm} = 86.99\ \mathrm{t{\cdot}m/cm}.

The centre of gravity. By Eq. (6.12),

xG=59.20−100×86.99×0.317722.1=59.20−0.35=58.85m.x_G = 59.20 - \frac{100 \times 86.99 \times 0.31}{7722.1} = 59.20 - 0.35 = 58.85\ \mathrm{m}.

6.12 In its departure condition the Series 60 ship displaces 7707 t and floats level at 6.366 m, the draught that Table 6.1 gives for this displacement, with TPC = 14.30 t/cm, xFx_F = 56.43 m and MCT 1 cm = 86.87 t·m/cm. The ship discharges all the cargo of hold 1 (271 t, centred 105.68 m forward of the AP) and hold 2 (693 t, centred 91.28 m forward of the AP), leaving 6743 t with xGx_G = 54.04 m. (a) Find the draughts by the incremental method of Sec. 6.3. (b) Find them from Eq. (6.11), with the hydrostatic values at the new displacement. Solved on the hull, the ship floats at 7.681 m aft and 3.320 m forward. Comment on the results.

Show answers

(a) 7.690 m aft, 3.373 m forward; (b) 7.891 m aft, 3.210 m forward

Show full solution

(a) The incremental method. The ship rises by 964/14.30=67.4964/14.30 = 67.4 cm. Both masses lie forward of F, and their removal trims the ship by the stern by

δt=271×(105.68−56.43)+693×(91.28−56.43)86.87=13,346.8+24,151.186.87=431.7cm.\delta t = \frac{271 \times (105.68 - 56.43) + 693 \times (91.28 - 56.43)}{86.87} = \frac{13{,}346.8 + 24{,}151.1}{86.87} = 431.7\ \mathrm{cm}.

Then δTA=−67.4+431.7×56.43/121.92=−67.4+199.8=132.4\delta T_A = -67.4 + 431.7 \times 56.43/121.92 = -67.4 + 199.8 = 132.4 cm and δTF=−67.4−431.7×65.49/121.92=−67.4−231.9=−299.3\delta T_F = -67.4 - 431.7 \times 65.49/121.92 = -67.4 - 231.9 = -299.3 cm, so the draughts are 7.690 m aft and 3.373 m forward.

(b) From the weight table. 6743 t lies 110.7/276.2=0.40110.7/276.2 = 0.40 of the way from 5.6 m to 5.8 m in Table 6.1, so T(xF)T(x_F) = 5.680 m, xB=59.56−0.40×0.08=59.53x_B = 59.56 - 0.40 \times 0.08 = 59.53 m, xF=57.73−0.40×0.34=57.59x_F = 57.73 - 0.40 \times 0.34 = 57.59 m and MCT 1 cm = 78.22+0.40×2.17=79.0978.22 + 0.40 \times 2.17 = 79.09 t·m/cm. Then

t=6743×(59.53−54.04)100×79.09=37,019.17909=4.681m,t = \frac{6743 \times (59.53 - 54.04)}{100 \times 79.09} = \frac{37{,}019.1}{7909} = 4.681\ \mathrm{m},

by the stern, so TA=5.680+4.681×57.59/121.92=5.680+2.211=7.891T_A = 5.680 + 4.681 \times 57.59/121.92 = 5.680 + 2.211 = 7.891 m and TF=7.891−4.681=3.210T_F = 7.891 - 4.681 = 3.210 m.

Comment. The trim of the hull, 4.361 m, is 3.6 % of the length, far beyond the range of either method. Method (b) uses the right hydrostatic values but still assumes a small trim, and it is 21 cm out at the stern. Method (a) happens to come closer, because its larger MCT 1 cm, that of the departure condition, offsets the curvature of Fig. 6.8 by the stern. Neither result should be used; at a trim like this the equilibrium has to be found on the hull.

6.13 The Series 60 ship floats at 7.12 m aft and 5.90 m forward. Find the displacement mass with the first trim correction, by entering Table 6.1 at the draught at F, and then with the second trim correction of Eq. (6.13), taking MCT 1 cm at 0.5 m above and below the draught at F.

Show answers

6.557 m; 7980.7 t; 6.6 t; 7987.3 t

Show full solution

The draught at F. The mean of the end draughts is 6.51 m, where xF=56.38−0.55×0.25=56.24x_F = 56.38 - 0.55 \times 0.25 = 56.24 m. With tt = 1.22 m,

T(xF)=7.12−1.22×56.24121.92=7.12−0.563=6.557m.T(x_F) = 7.12 - 1.22 \times \frac{56.24}{121.92} = 7.12 - 0.563 = 6.557\ \mathrm{m}.

The first trim correction. 6.557 m lies 0.785 of the way from 6.4 m to 6.6 m, so Δm=7754.9+0.785×287.6=7980.7\Delta_m = 7754.9 + 0.785 \times 287.6 = 7980.7 t. At the mean draught the table would give 7913.1 t.

The second trim correction. MCT 1 cm is 93.54+0.285×2.30=94.2093.54 + 0.285 \times 2.30 = 94.20 t·m/cm at 7.057 m and 82.75+0.285×2.32=83.4182.75 + 0.285 \times 2.32 = 83.41 t·m/cm at 6.057 m, a change of 10.79 t·m/cm per metre, and the second trim correction is

δΔm=50×1.222121.92×10.79=6.6t,\delta\Delta_m = \frac{50 \times 1.22^2}{121.92} \times 10.79 = 6.6\ \mathrm{t},

so the displacement mass is 7980.7+6.6=7987.37980.7 + 6.6 = 7987.3 t. Computed directly on the hull, the displacement mass at these draughts is 7987.8 t.

6.14 A ship 150 m between perpendiculars displaces 12,000 t and floats level at 8.00 m in sea water, with B at xBx_B = 76.80 m and F at xFx_F = 73.50 m forward of the AP. Its TPC in sea water is 24.0 t/cm, and its MCT 1 cm in sea water at the new draught will be 170 t·m/cm. The ship moves into dock water of density 1.010 t/m³. Find the sinkage, the change of trim and the new draughts.

Show answers

7.4 cm; 3.5 cm by the head; 8.057 m aft; 8.092 m forward

Show full solution

The sinkage. By Eq. (3.16), the ship sinks by

δT=12,00024.0×1.025−1.0101.010=500×0.01485=7.4cm.\delta T = \frac{12{,}000}{24.0} \times \frac{1.025 - 1.010}{1.010} = 500 \times 0.01485 = 7.4\ \mathrm{cm}.

The shift of B. The volume grows from 12,000/1.025=11,707.312{,}000/1.025 = 11{,}707.3 m³ to 12,000/1.010=11,881.212{,}000/1.010 = 11{,}881.2 m³, a layer of 173.9 m³ centred near F. By Eq. (6.14), B moves through

δxB=173.9×(73.50−76.80)11,881.2=−0.0483m.\delta x_B = \frac{173.9 \times (73.50 - 76.80)}{11{,}881.2} = -0.0483\ \mathrm{m}.

The change of trim. In dock water MCT 1 cm is 170×1.010/1.025=167.5170 \times 1.010/1.025 = 167.5 t·m/cm, so

δt=12,000×(−0.0483)100×167.5=−0.035m,\delta t = \frac{12{,}000 \times (-0.0483)}{100 \times 167.5} = -0.035\ \mathrm{m},

3.5 cm by the head.

The draughts. The draught at F becomes 8.074 m, so TA=8.074−0.035×73.50/150=8.074−0.017=8.057T_A = 8.074 - 0.035 \times 73.50/150 = 8.074 - 0.017 = 8.057 m and TF=8.057+0.035=8.092T_F = 8.057 + 0.035 = 8.092 m.

6.15 A ship 110 m between perpendiculars displaces 6000 t. A mass of 30 t of ballast is pumped 80 m aft, and the trim changes by 0.215 m by the stern. Find the longitudinal metacentric height of the ship and its MCT 1 cm.

Show answers

204.7 m; 111.6 t·m/cm

Show full solution

By Eq. (6.16),

GML=30×80×1106000×0.215=264,0001290=204.7m.\mathrm{GM}_\mathrm{L} = \frac{30 \times 80 \times 110}{6000 \times 0.215} = \frac{264{,}000}{1290} = 204.7\ \mathrm{m}.

The moment of 2400 t·m changed the trim by 21.5 cm, so MCT 1 cm = 2400/21.5=111.62400/21.5 = 111.6 t·m/cm.

6.16 A river barge, a box 70 m long and 11 m wide, floats at 2.5 m in fresh water with KG = 2.8 m. Its single cargo tank, 60 m long and 10 m wide, is partly filled with oil of density 0.90 t/m³. Find the longitudinal metacentric height of the barge and its MCT 1 cm, first ignoring the free surface and then allowing for it.

Show answers

161.78 m and 44.49 t·m/cm; 77.63 m and 21.35 t·m/cm

Show full solution

Ignoring the free surface. The barge displaces 70×11×2.5=192570 \times 11 \times 2.5 = 1925 m³, or 1925 t in fresh water, with KB = 1.25 m and BML=L2/(12T)=702/30=163.33\mathrm{BM}_\mathrm{L} = L^2/(12T) = 70^2/30 = 163.33 m. Then

GML=1.25+163.33−2.8=161.78m,MCT1cm=1925×161.78100×70=44.49t⋅m/cm.\mathrm{GM}_\mathrm{L} = 1.25 + 163.33 - 2.8 = 161.78\ \mathrm{m}, \qquad \mathrm{MCT\,1\,cm} = \frac{1925 \times 161.78}{100 \times 70} = 44.49\ \mathrm{t{\cdot}m/cm}.

Allowing for the free surface. The surface of the oil has iL=10×603/12=180,000i_L = 10 \times 60^3/12 = 180{,}000 m⁴ about its transverse axis, so

GGv,L=0.90×180,0001925=84.16m,\mathrm{GG}_{v,L} = \frac{0.90 \times 180{,}000}{1925} = 84.16\ \mathrm{m},

and GML=161.783−84.156=77.63\mathrm{GM}_\mathrm{L} = 161.783 - 84.156 = 77.63 m, with MCT 1 cm = 1925×77.63/7000=21.351925 \times 77.63/7000 = 21.35 t·m/cm.

Comment. A tank that runs almost the whole length of the barge halves its longitudinal stability, and a given moment trims the barge twice as much as the calculation without the free surface gives.

6.17 A ship 150.0 m between perpendiculars floats level at 7.80 m in sea water, with F 72.0 m forward of the AP and MCT 1 cm = 160 t·m/cm. The tips of its propellers reach 0.25 m below the keel at 6.0 m forward of the AP, and its sonar dome reaches 0.85 m below the keel at 138.0 m. (a) Find the navigational draught. (b) Find the trim that makes the navigational draught least, and that draught. (c) Find the mass of ballast that must be pumped from a tank centred 125.0 m forward of the AP to a tank centred 15.0 m forward of the AP to give that trim.

Show answers

(a) 8.650 m; (b) 0.682 m by the stern, 8.350 m; (c) 99.2 t

Show full solution

(a) Level. The ship draws 7.80+0.25=8.057.80 + 0.25 = 8.05 m at the propeller tips and 7.80+0.85=8.657.80 + 0.85 = 8.65 m at the dome, so the navigational draught is 8.650 m.

(b) The least navigational draught. The draughts at the two projections are equal when

t=(0.85−0.25)×150.0138.0−6.0=90.0132.0=0.682m,t = \frac{(0.85 - 0.25) \times 150.0}{138.0 - 6.0} = \frac{90.0}{132.0} = 0.682\ \mathrm{m},

by the stern. The line joining the lowest points of the two projections lies 0.25+0.60×(72.0−6.0)/132.0=0.25+0.30=0.550.25 + 0.60 \times (72.0 - 6.0)/132.0 = 0.25 + 0.30 = 0.55 m below the keel at F, so the least navigational draught is 7.80+0.55=8.3507.80 + 0.55 = 8.350 m. The keel at the AP is then at 7.80+0.682×72.0/150.0=8.1277.80 + 0.682 \times 72.0/150.0 = 8.127 m and does not govern.

(c) The ballast. The trim must change by 68.2 cm by the stern, which needs a moment of 68.2×160=10,91268.2 \times 160 = 10{,}912 t·m. The ballast moves 125.0−15.0=110.0125.0 - 15.0 = 110.0 m aft, so its mass is 10,912/110.0=99.210{,}912/110.0 = 99.2 t.

6.18 Upright, the Series 60 ship would float level at 6.30 m in sea water. It arrives at a lock that admits no ship drawing more than 6.40 m, with a list of 1.5° to port. Its flat of keel extends 5.77 m to each side of the centreline amidships. Taking the list about the centreline at the waterline, (a) find the deepest draught, and (b) find the largest list with which the ship may enter the lock.

Show answers

(a) 6.449 m; (b) 1.00°

Show full solution

(a) The deepest draught. At a small list the deepest point lies at the outer edge of the flat of keel, 5.77 m from the centreline at the height of the keel, so the deepest draught is

6.30cos1.5∘+5.77sin1.5∘=6.2978+0.1510=6.449m.6.30\cos 1.5^\circ + 5.77\sin 1.5^\circ = 6.2978 + 0.1510 = 6.449\ \mathrm{m}.

(b) The largest list. The list must satisfy 6.30cosφ+5.77sinφ=6.406.30\cos\varphi + 5.77\sin\varphi = 6.40. Since cosφ\cos\varphi is close to 1, a first estimate is sinφ=0.10/5.77=0.0173\sin\varphi = 0.10/5.77 = 0.0173, or 0.99°. With cos0.99∘\cos 0.99^\circ = 0.99985 the first term is 6.2991 m, so

sinφ=6.40−6.29915.77=0.01749,φ=1.00∘.\sin\varphi = \frac{6.40 - 6.2991}{5.77} = 0.01749 , \qquad \varphi = 1.00^\circ .

The list has to come off by a third before the ship may enter. A box of its breadth, 16.26 m, would draw 6.511 m at 1.5°.

Symbols introduced in this chapter

Symbols defined in earlier chapters, among them tt, θ\theta, φ\varphi, TPC, MCT 1 cm, xBx_B, xFx_F, xGx_G, AWA_W, ILI_L, CBC_B, BML\mathrm{BM}_\mathrm{L} and GML\mathrm{GM}_\mathrm{L}, keep their meaning.

Symbol Meaning Unit
T(x)T(x) draught at a distance xx forward of the AP m
T(xF)T(x_F) draught at the centre of flotation, the equivalent even-keel draught or true mean draught m
Ta′T_a', Tf′T_f' draughts read at the aft and forward marks m
TlimT_{\mathrm{lim}} limiting draught of a lock, channel or berth m
xax_a, xfx_f positions of the aft and forward draught marks, forward of the AP m
mm; xx; x1x_1, x2x_2 a mass loaded, discharged or moved; its position; its positions before and after a move t; m
dd distance through which a mass is moved along the ship m
x0x_0 position of a point whose draught a loaded mass leaves unchanged m
mPm_P, mQm_Q; xPx_P, xQx_Q two masses loaded to reach required draughts; their positions t; m
p1p_1, p2p_2; xp1x_{p1}, xp2x_{p2} depths below the keel of the lowest points of an aft and a forward projection; their positions m
VkV_k speed through the water knots
δt\delta t change of trim, positive by the stern cm or m
δT\delta T bodily sinkage cm or m
δTA\delta T_A, δTF\delta T_F changes of the draughts at the perpendiculars cm or m
δΔm\delta\Delta_m second trim correction to the displacement t
vv, ∇1\nabla_1 volume of the layer added when the water becomes less dense; volume before the change m³
δxB\delta x_B movement of B along the ship m
GGv,L\mathrm{GG}_{v,L} virtual rise of G for inclinations along the ship, from free surfaces m
iLi_L second moment of a free surface about its transverse axis m⁴
bb, ll breadth of a strip of waterplane or of a tank; length of a tank m
hth_t, ff depth of a tank; fraction of its depth filled m; –

Corrections

Corrections to version 1.0, released on 3 November 2026, with their dates.

References

  1. Transportation Safety Board of Canada. (1997). Marine occurrence report: Bottom contact by the bulk carrier “Steel Flower” in the Welland Canal, 28 April 1996 (Report No. M96C0022). Retrieved November 2, 2026, from https://www.tsb-bst.gc.ca/eng/rapports-reports/marine/1996/m96c0022/m96c0022.html Cited: ↑ · ↑ · ↑ · ↑ · ↑ · ↑
  2. Moore, C. S. (2010). Intact stability (J. R. Paulling, Ed.; Principles of Naval Architecture Series). Society of Naval Architects and Marine Engineers. Cited: ↑ p. 14 · ↑ pp. 58–59 · ↑ p. 56 · ↑ p. 59 · ↑ p. 14 · ↑ p. 58 · ↑ p. 73 · ↑ p. 57 · ↑ p. 57 · ↑ p. 57 · ↑ p. 54 · ↑ p. 56 · ↑ p. 55 · ↑ p. 55 · ↑ p. 56 · ↑ p. 55 · ↑ p. 55 · ↑ pp. 4–5 · ↑ pp. 34–35 · ↑ p. 54
  3. Biran, A., & López-Pulido, R. (2014). Ship hydrostatics and stability (2nd ed.). Butterworth-Heinemann. Cited: ↑ p. 180 · ↑ p. 104 · ↑ p. 177 · ↑ p. 177 · ↑ p. 351
  4. Barrass, C. B., & Derrett, D. R. (2006). Ship stability for masters and mates (6th ed.). Butterworth-Heinemann. Cited: ↑ p. 492 · ↑ p. 144 · ↑ p. 281 · ↑ p. 150 · ↑ pp. 148–149 · ↑ p. 151 · ↑ pp. 153–156 · ↑ p. 153 · ↑ p. 159 · ↑ pp. 159–160 · ↑ pp. 156–158 · ↑ p. 159 · ↑ pp. 189–190 · ↑ p. 191 · ↑ p. 324 · ↑ p. 324 · ↑ p. 326 · ↑ p. 327 · ↑ pp. 326–327 · ↑ p. 166 · ↑ pp. 492, 496 · ↑ pp. 375–378 · ↑ pp. 163–165
  5. Kemp, J. F., & Young, P. (2001). Ship stability: Notes and examples (3rd ed., rev. C. B. Barrass). Butterworth-Heinemann. Cited: ↑ p. 89 · ↑ p. 101 · ↑ p. 102 · ↑ pp. 101–103 · ↑ pp. 91–92 · ↑ pp. 96–97 · ↑ pp. 97–99 · ↑ pp. 84–85 · ↑ p. 102 · ↑ pp. 104–106 · ↑ p. 102
  6. Tupper, E. C. (2013). Introduction to naval architecture (5th ed.). Butterworth-Heinemann. Cited: ↑ p. 55 · ↑ p. 59 · ↑ p. 57 · ↑ pp. 56–57 · ↑ p. 57 · ↑ p. 56 · ↑ p. 60 · ↑ p. 66 · ↑ p. 86
  7. Attwood, E. L. (1899). Text-book of theoretical naval architecture. Longmans, Green, and Co. (Public domain.) Cited: ↑ p. 148 · ↑ pp. 143–144 · ↑ pp. 145–147 · ↑ p. 156, Example 5
  8. IMO. (2024). SOLAS: Consolidated edition 2024 (Sales No. IH110E). International Maritime Organization. Cited: ↑ reg. II-1/5-1.2.1
  9. Wawrzyński, W. (2024). The second trim correction in draught survey procedure: Accuracy analysis. TransNav, the International Journal on Marine Navigation and Safety of Sea Transportation, 18(3), 695–703. https://doi.org/10.12716/1001.18.03.25 Cited: ↑ · ↑
  10. Yun, L., Bliault, A., & Rong, H. Z. (2019). High speed catamarans and multihulls: Technology, performance, and applications. Springer. https://doi.org/10.1007/978-1-4939-7891-5 Cited: ↑ p. 78
  11. IMO. (2020). International Code on Intact Stability, 2008 (2020 ed.). International Maritime Organization. (Includes the Explanatory Notes, MSC.1/Circ.1281.) Cited: ↑ Part B, 4.1.4.1 · ↑ Part B, 4.1.6.2.3 · ↑ Part B, 3.5.1 · ↑ Part B, 3.6.7.4 · ↑ Part A, 2.1.7
  12. IMO. (2007). Guidelines for the approval of stability instruments (MSC.1/Circ.1229, 11 January 2007). International Maritime Organization. Cited: ↑ annex, para. 4.6 and table
  13. IACS. (2020). Computer software for onboard stability calculations (UR L5, Rev. 4, June 2020). International Association of Classification Societies. Retrieved October 9, 2026, from https://iacs.s3.af-south-1.amazonaws.com/wp-content/uploads/2022/02/17101147/ur-l5rev4.pdf Cited: ↑ Table 1 and Note 2
  14. Great Lakes St. Lawrence Seaway. (2026b). Seaway Notice No. 5 – 2026 (2 April 2026). Retrieved October 11, 2026, from https://greatlakes-seaway.com/wp-content/uploads/2026/04/notice20260402a_en.pdf Cited: ↑
  15. Great Lakes St. Lawrence Seaway. (2026a). The Seaway handbook: Seaway practices and procedures (2026 ed., amended March 2026). Retrieved October 11, 2026, from https://greatlakes-seaway.com/wp-content/uploads/2026/03/Seaway_Handbook_print_en2026.pdf Cited: ↑ Section 29 · ↑ Section 30
  16. Panama Canal Authority. (2026). Vessel requirements (OP Notice to Shipping No. N-1-2026, 1 January 2026). Retrieved November 2, 2026, from https://pancanal.com/wp-content/uploads/2021/08/N01-2026-Vessel-Requirements_BMV.pdf Cited: ↑
  17. Pilbara Ports. (2025). Port of Port Hedland port handbook (internal amendment table: Version 1, August 2025; website file updated 10 September 2026). Retrieved November 2, 2026, from https://www.pilbaraports.com.au/about-pilbara-ports/publications/forms-and-publications/forms-and-publications/handbook/2026/september/port-of-port-hedland-port-handbook Cited: ↑
  18. IMO. (2018). Load lines: Consolidated edition 2018. International Maritime Organization. Cited: ↑ Annex I, reg. 39(1)
  19. Accident Investigation Board Norway. (2012). Report on investigation of marine accident, Langeland LDJB3, founder in the Kosterfjord, Sweden 31 July 2009 (Marine report 2012/08). Retrieved October 11, 2026, from https://nsia.no/Marine/Published-reports/2012-08-eng Cited: ↑
  20. IMO. (2026). 2024 Guidelines for the development of a Ship Energy Efficiency Management Plan (SEEMP), as amended (resolution MEPC.395(82), as amended by resolutions MEPC.401(83) and MEPC.413(84)) (MEPC.1/Circ.925, 5 June 2026). International Maritime Organization. Retrieved October 11, 2026, from https://wwwcdn.imo.org/localresources/en/OurWork/Environment/Documents/MEPC.1-Circ.925%20-%202024%20Guidelines%20For%20The%20Development%20Of%20A%20Ship%20Energy%20Efficiency%20Management%20Plan%20(Seemp),%20A…%20(Secretariat)%20(1).pdf Cited: ↑ paragraphs 5.3.1 and 5.3.2
  21. Shivachev, E., Khorasanchi, M., Day, S., & Turan, O. (2020). Impact of trim on added resistance of KRISO container ship (KCS) in head waves: An experimental and numerical study. Ocean Engineering, 211, 107594. https://doi.org/10.1016/j.oceaneng.2020.107594 Cited: ↑
  22. Reichel, M., Minchev, A., & Larsen, N. L. (2014). Trim optimisation: Theory and practice. TransNav, the International Journal on Marine Navigation and Safety of Sea Transportation, 8(3), 387–392. https://doi.org/10.12716/1001.08.03.09 Cited: ↑
  23. Martić, I., Anušić, B., Degiuli, N., & Grlj, C. G. (2024). Numerically investigating the effect of trim on the resistance of a container ship in confined and shallow water. Applied Sciences, 14(15), 6570. https://doi.org/10.3390/app14156570 Cited: ↑
  24. FORCE Technology. (n.d.). Let CFD do the trim optimisation for you. Retrieved October 11, 2026, from https://forcetechnology.com/en/insights/articles/cfd-trim-optimization Cited: ↑